Entries by Town of Palm Beach

­Traffic Impacts for the Week of 02/19/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects

­Traffic Impacts for the Week of 02/19/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects **NO WORK ON MONDAY 02/19/2024 IN OBSERVANCE OF PRESIDENT’S DAY**  **OBSERVED TOWN HOLIDAY** PHASE 4 NORTH FPL Will Continue Wire and Pole Removal […]

­Traffic Impacts for the Week of 02/12/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects

PHASE 4 NORTH FPL Will Continue Wire Removal Along North Ocean Starting At List Road And Heading North With Wire Removal & Topping Of Poles.  PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding Private Side Services – Terminations – Country Club Road, Fairview Between Northlake Way & North County Road. – No Traffic Impacts Private […]

­Traffic Impacts for the Week of 02/05/2024 for the Phase 4 North, 5 North, Phase 6 North, Phase 7 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects

PHASE 4 NORTH FPL Will Continue Wire Removal Along North Lakeway Early In The Week Then Move To North Ocean Starting At List Road And Heading North With Wire Removal PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding HDD – North County Road Between The Beach Club & Ocean Lane – Shoulder Will Be Closed […]

­Traffic Impacts for the Week of 01/29/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding Pulling Wire & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Wire Pulling & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding HDD – Northlake […]

­Traffic Impacts for the Week of 01/22/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding Pulling Wire & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Wire Pulling & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding HDD – N. […]

­Traffic Impacts for the Week of 01/15/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding Pulling Wire & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Equipment & Conduit Installation – Casa Bendita Between North County Road and the Cul-de-sac – Road Closed Local Traffic Only – Traffic Maintained Equipment & […]

­Traffic Impacts for the Week of 01/08/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding Pulling Wire & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained HDD – Northlake Way Between Southland & Via Linda – Detour To Be Implemented – Detour Plan To Be Submitted PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding HDD – Northlake Way Between […]

­Traffic Impacts for the Week of 12/25/2023 & 01/01/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

**THERE WILL BE NO WORK THE WEEK OF 12/25/2023 IN OBSERVANCE OF CHRISTMAS AND NEW YEAR HOLIDAYS** WEEK OF 01/01/2024.  WORK TO BEGIN ON WEDNESDAY 01/03/2024 IN OBSERVANCE OF THE TOWN’S HOLIDAY SCHEDULE PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding Pulling Wire & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained […]

­Traffic Impacts for the Week of 12/18/2023 for the Phase 5 North, Phase 6 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects

The North projects will work through Wednesday 12/20/2023, then shut down and return on Wednesday 01/03/2024. PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding Pulling Wire & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Wire Pulling & Terminations – Various Locations – No […]

­Traffic Impacts for the Week of 12/11/2023 for the Phase 5 North, Phase 6 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 5 NORTH Horizontal Directional Drilling / Undergrounding Pulling Wire & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding HDD – Northlake Way Between North Woods Road & Kawama – ROAD CLOSED – VARIOUS DETOURS TO IMPLEMENTED AS WORK PROGRESSES  – Traffic Maintained Conduit […]