Entries by Town of Palm Beach

Traffic Impacts for the Week of 02/27/2023 for the Phase 4 North, Phase 5 North,  Phase 6 North, Phase 3 South, Phase 4 South, and Phase 5 South Projects

PHASE 4 NORTH  Horizontal Directional Drilling / Undergrounding Private Side Service Connections — Various Locations (Dependent on FPL Switching Orders) – Traffic Maintained PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding HDD – Plantation Road Between Northlake Way & Crest Road. – Road Closed Local Traffic Only – Traffic Maintained HDD – Hi Mount Road (North End Services) – Road […]

Traffic Impacts for the Week of 02/27/2023 for the Phase 4 North, Phase 5 North,  Phase 6 North, Phase 3 South, Phase 4 South, and Phase 5 South projects

PHASE 4 NORTH  Horizontal Directional Drilling / Undergrounding Private Side Service Connections — Various Locations (Dependent on FPL Switching Orders) – Traffic Maintained PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding HDD – Northlake Way Between Via Linda & Plantation – Lane Closure To Be Implemented – Traffic Maintained. HDD – Plantation Road Between Northlake Way & Crest Road. – Road Closed […]

Traffic Impacts for the Week of 02/20/2023 for the Phase 4 North, Phase 5 North,  Phase 6 North, Phase 3 South, Phase 4 South, and Phase 5 South Projects

** NO WORK ON MONDAY 02/20/2023 IN OBSERVANCE OF PRESIDENTS DAY** PHASE 4 NORTH  Horizontal Directional Drilling / Undergrounding Private Side Service Connections — Various Locations – Traffic Maintained PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding HDD – Northlake Way Between Via Linda & Plantation – Lane Closure To Be Implemented – Traffic Maintained. HDD – Plantation Road Between […]

Traffic Impacts for the Week of 02/13/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, and Phase 5 South Projects

PHASE 4 NORTH  Horizontal Directional Drilling / Undergrounding Private Side Service Connections — Various Locations – Traffic Maintained PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding HDD – Northlake Way Between West Indies & Plantation – Lane Closure To Be Implemented – Traffic Maintained. Equipment & Conduit Installation – Northlake Way Between El Dorado & Via Linda – Lane Closure To […]

Traffic Impacts for the week of 02/06/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, and Phase 5 South Projects

PHASE 4 NORTH  Horizontal Directional Drilling / Undergrounding Private Side Service Connections — Various Locations – Traffic Maintained PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding HDD – Northlake Way Between El Dorado & West Indies – Lane Closure To Be Implemented – Traffic Maintained. Equipment & Conduit Installation – Northlake Way Between El Dorado & West Indies Road – Road […]

Traffic Impacts for the week of 01/30/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, and Phase 5 South Projects

PHASE 4 NORTH Horizontal Directional Drilling / Undergrounding Private Side Service Connections — Various Locations – Traffic Maintained PHASE 5 NORTH Horizontal Directional Drilling / Undergrounding HDD – Northlake Way Between El Dorado & West Indies – Lane Closure to Be Implemented – Traffic Maintained. Equipment & Conduit Installation – Plantation Road and Southland Road Between N. County Road and […]

Traffic Impacts for the Week of 01/23/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, And Phase 5 South Projects

PHASE 4 NORTH  Horizontal Directional Drilling / Undergrounding Private Side Service Connections — Various Locations – Traffic Maintained PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding HDD – Northlake Way Between El Dorado & West Indies – Lane Closure To Be Implemented – Traffic Maintained. Equipment & Conduit Installation – Plantation Road And Southland Road Between N. County Road and […]

Traffic Impacts for the Week Of 01/16/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 2 South, Phase 3 South, Phase 4 South, and Phase 5 South Projects

PHASE 4 NORTH  Horizontal Directional Drilling / Undergrounding Private Side Service Connections – Various Locations – Traffic Maintained PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding HDD – Northlake Way Between El Dorado & West Indies – Lane Closure To Be Implemented – Traffic Maintained Equipment & Conduit Installation – Plantation Road Between N. County Road and Northlake Way – Road […]

Traffic Impacts for the Week of 01/09/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 2 South, Phase 3 South, Phase 4 South, and Phase 5 South Projects

PHASE 4 NORTH  Horizontal Directional Drilling / Undergrounding Private Side Service Connections — Various Locations – Traffic Maintained PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding HDD – Plantation Road, Southland Road Between Northlake Way & N. County Road –  HDD – Northlake Way Between El Dorado & Plantation Road – Lane Closure to be Implemented – Traffic Maintained. Pulling Primary […]

Traffic Impacts for the Week of 01/02/2023 for the Phase 4 North, Phase 5 North,  Phase 6 North, Phase 2 South, Phase 3 South, Phase 4 South, And Phase 5 South Projects

WORK IS ON HOLD FROM 12/23/2022 THRU 01/02/2023 FOR THE HOLIDAY SEASON.  PHASE 4 NORTH  Horizontal Directional Drilling / Undergrounding Private Side Service Connections — Pending FPL Switching Orders – Various Locations – Traffic Maintained PHASE 5 NORTH Horizontal Directional Drilling / Undergrounding HDD – Plantation Road, Southland Road Between Northlake Way & N. County Road –  HDD […]