Power Lines Sparking or Other Hazardous Conditions
If you see power lines sparking or other hazardous conditions,…
Easement Abandonment Process
Town Code of Ordinances, Chapter 106, Article IV, requires an application to abandon a public utility easement to be made in writing on an application form provided by the Town.
Pole & Wire Removal is Complete - Phase 1 South
Phase 1 South Overhead System Decommission is now 100% complete…
The Town of Palm Beach Would like to Thank the Following Property Owners
The Town of Palm Beach would like to thank and recognize the…
Traffic Impacts for the Week of 05/13/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 4 NORTH
FPL – Wire & Pole Removal Via Crane on…
Traffic Impacts for the Week of 05/06/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 4 NORTH
FPL – Wire & Pole Removal Via Crane on…
Traffic Impacts for the Week of 04/29/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 4 NORTH
FPL - Pole Removal Via Crane on List Road &…
Traffic Impacts for the Week of 04/22/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 4 NORTH
FPL - Pole Removal Via Crane on List Road -…
Traffic Impacts for the Week of 04/15/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 4 NORTH
FPL - Pole Removal Via Crane on Monterey &…
Traffic Impacts for the Week of 04/08/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 4 NORTH
FPL - Pole Removal (8 Each) Via Crane…
Traffic Impacts for the Week of 04/01/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 4 NORTH
FPL - Pole Removal Via Crane on Colonial (First…
Traffic Impacts for the Week of 03/25/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 4 NORTH
FPL - Pole Removal Via Crane on El Pueblo Way…
Traffic Impacts for the Week of 03/18/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 4 NORTH
FPL - Pole Removal Via Crane on El Pueblo Way…
Traffic Impacts for the Week of 03/11/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 4 NORTH
FPL Will Continue Wire and Pole Removal Along…