Pole & Wire Removal is Complete - Phase 1 South
Phase 1 South Overhead System Decommission is now 100% complete…

The Town of Palm Beach Would like to Thank the Following Property Owners
The Town of Palm Beach would like to thank and recognize the…


Power Lines Sparking or Other Hazardous Conditions
If you see power lines sparking or other hazardous conditions,…

Easement Abandonment Process
Town Code of Ordinances, Chapter 106, Article IV, requires an application to abandon a public utility easement to be made in writing on an application form provided by the Town.

Undergrounding Program - Status Update as of March 30 2020
The undergrounding project continues to move forward. Town…

Undergrounding Coffee Meetings - Cancelled for April
Community Meetings
The health and safety of Town employees,…

Pole & Wire Removal in Progress - Phase 1 South
The following images were taken in Ibis Isle after pole and…

Pole & Wire Removal is Complete - Phase 1 North
Phase 1 North is 100% complete as of September 2019. Image…

$54,000 in additional savings
Working with FPL the Town has been able to adjust the design…

North End Easement Reduction
Saves: Reduction of easements on the North End
Raves: UUTF…

Phase 1 North Savings
Saves: A walk through of Phase 1 North was conducted to determine…