Traffic Impacts Week of 02/28/2022
Below are the traffic impacts for the week of 2/28/2022 for the phase 4 north, phase 5 north, phase 2 south, phase 3 south, and phase 4 south projects.
PHASE 4 NORTH
Horizontal Directional Drilling / Undergrounding
Northlake Way & North Ocean Blvd.–Blowing Strings In Conduits. Lane Closure To Be Implemented. Traffic Maintained.
FPL WORK
Northlake Way Between Orange Grove & Via Marila– Monday 02-28-2022 & Tuesday 03-01-2022. Setting Termination Poles. Lane Closure To Be Implemented. Traffic Maintained.
North Ocean Blvd Between List Road & Via Marila– Tuesday 03-01-2022 & Wednesday 03-02-2022. Termination Pole Set Up. Lane Closure To Be Implemented. Traffic Maintained.
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Hi Mount Road–HDD. Traffic Maintained.
Ridgeview Road–HDD from North County To Northlake Way. Lane Closure To Be Implemented. Traffic Maintained.
PHASE 2 SOUTH
Horizontal Directional Drilling / Undergrounding
Miscellaneous Transformer Energizing Dependent On Switching Orders From FPL.
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD — El Bravo Way, and S. County Road From Banyan Road North To Island Road
HDD — Golfview Alleyway
Conduit Connections, Equipment Installation, Road Restoration — Banyan Road and S. County Road from Banyan Road north to El Vedado Road.
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD — Peruvian Avenue between South County Road and South Ocean Boulevard
“LOCAL TRAFFIC ONLY”