Lane Closure

Traffic Impacts Week of 02/28/2022

 

Below are the traffic impacts for the week of 2/28/2022 for the phase 4 north,  phase 5 north, phase 2 south, phase 3 south, and phase 4 south projects.

PHASE 4 NORTH  

 Horizontal Directional Drilling / Undergrounding

Northlake Way & North Ocean Blvd.–Blowing Strings In Conduits. Lane Closure To Be Implemented. Traffic Maintained.

FPL WORK

Northlake Way Between Orange Grove & Via Marila– Monday 02-28-2022 & Tuesday 03-01-2022. Setting Termination Poles. Lane Closure To Be Implemented. Traffic Maintained.

North Ocean Blvd Between List Road & Via Marila– Tuesday 03-01-2022 & Wednesday 03-02-2022. Termination Pole Set Up. Lane Closure To Be Implemented. Traffic Maintained.

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

Hi Mount Road–HDD. Traffic Maintained.

Ridgeview Road–HDD from North County To Northlake Way. Lane Closure To Be Implemented. Traffic Maintained.

PHASE 2 SOUTH 

Horizontal Directional Drilling / Undergrounding 

Miscellaneous Transformer Energizing Dependent On Switching Orders From FPL.

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding 

HDD — El Bravo Way, and  S. County Road From Banyan Road North To Island Road

HDD — Golfview Alleyway

Conduit Connections, Equipment Installation, Road Restoration — Banyan Road and S. County Road from Banyan Road north to El Vedado Road.

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD — Peruvian Avenue between South County Road and South Ocean Boulevard

“LOCAL TRAFFIC ONLY”