Entries by Town of Palm Beach

Traffic impacts below for the week of 07/13/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Punch List items – Various Locations – No Traffic Impact PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding HDD on Pendleton Ave (West end at S. County Rd.) – Lane Closure – Local Traffic Only – Traffic Maintained HDD on S. County Rd. between Pendleton Ave and […]

Traffic impacts below for the week of 07/06/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Punch List items – various locations – No traffic impact PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts. Overhead Wreck Out – N. County Road between Breakers Row and Royal Poinciana Way – Northbound lane Closure – Traffic Maintained.  […]

Traffic impacts below for the week of 06/29/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

**THERE WILL BE NO WORK ON FRIDAY JULY 3, 2026 IN OBSERVANCE OF THE 4TH OF JULY HOLIDAY** PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders. Punch List items – various locations – No traffic impact […]

Traffic impacts below for the week of 06/22/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders. Punch List items – various locations – No traffic impact PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts. Overhead Wreck […]

Traffic impacts below for the week of 06/15/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders / Easement PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts. **Overhead Wreck Out – S. County Road At Seabreese – […]

Traffic impacts below for the week of 06/01/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders / Easement PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts. Overhead Wreck Out – Seabreeze – Working From West End […]

Traffic impacts below for the week of 05/25/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders / Easement PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts. Overhead Wreck Out – Seabreeze – Working From West End […]

Traffic impacts below for the week of 05/18/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders / Easement PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts. Overhead Wreck Out – Seabreeze – Working From West End […]

Traffic impacts below for the week of 05/11/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders / Easement PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts. Overhead Wreck Out – Cocoanut Row – Working From Royal […]

Traffic impacts below for the week of 05/04/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders / Easement PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts. Overhead Wreck Out – Cocoanut Row – Working From Royal […]