Entries by Town of Palm Beach

The traffic impacts below for the week of 08/24/2026 for Phases 6S, 7N, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Punch List items – Various Locations – No Traffic Impact Overhead Wreck Out – Pole & Wire Removal – Laurian Lane PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Overhead Wreck Out – Pole & Wire Removal – Pendelton & Cocoanut Row – Lane Closure – Traffic […]

Traffic impacts for the week of 08/17/2026 for Phases 6S, 7N, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Punch List items – Various Locations – No Traffic Impact PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Overhead Wreck Out – Pole & Wire Removal – Royal Poinciana Between North County Road & Cocoanut Row – Lane Closure – Traffic Maintained FInish Punch List Items – […]

Traffic impacts below for the week of 08/10/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Punch List items – Various Locations – No Traffic Impact PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Overhead Wreck Out – Pole & Wire Removal – North County Road – Breaker Row to Royal Poinciana  – Lane Closure – Traffic Maintained Overhead Wreck Out – Pole […]

Traffic impacts below for the week of 08/03/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Punch List items – Various Locations – No Traffic Impact PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Overhead Wreck Out – Pole & Wire Removal – North County Road – Via Bethesda to Royal Poinciana  – Lane Closure – Traffic Maintained PHASE 7 SOUTH Horizontal Directional […]

Traffic impacts below for the week of 07/27/2026 for Phases 7N, 5S, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Punch List items – Various Locations – No Traffic Impact PHASE 5 SOUTH Horizontal Directional Drilling / Undergrounding Concrete Restoration – 417 Peruvian Ave – Parking Spots to be blocked – Traffic Maintained.  PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Complete Remaining Miscellaneous Punch List Items […]

Traffic impacts below for the week of 07/20/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Punch List items – Various Locations – No Traffic Impact PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts. HDD – South County Road Between Pendleton & Pinewalk – Lane Closure To Be Implemented – Traffic Maintained Tie-In On Pendleton West Of South […]

Traffic impacts below for the week of 07/13/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Punch List items – Various Locations – No Traffic Impact PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding HDD on Pendleton Ave (West end at S. County Rd.) – Lane Closure – Local Traffic Only – Traffic Maintained HDD on S. County Rd. between Pendleton Ave and […]

Traffic impacts below for the week of 07/06/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Punch List items – various locations – No traffic impact PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts. Overhead Wreck Out – N. County Road between Breakers Row and Royal Poinciana Way – Northbound lane Closure – Traffic Maintained.  […]

Traffic impacts below for the week of 06/29/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

**THERE WILL BE NO WORK ON FRIDAY JULY 3, 2026 IN OBSERVANCE OF THE 4TH OF JULY HOLIDAY** PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders. Punch List items – various locations – No traffic impact […]

Traffic impacts below for the week of 06/22/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders. Punch List items – various locations – No traffic impact PHASE 6 SOUTH Horizontal Directional Drilling / Undergrounding Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts. Overhead Wreck […]