Entries by Town of Palm Beach

Traffic impacts below for the week of 04/27/2026 for Phases 7N, 4S, 5S, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders / Easement PHASE 4 SOUTH Horizontal Directional Drilling / Undergrounding  Complete Remaining Miscellaneous Punch List Items  No Traffic Impacts PHASE 5 SOUTH Horizontal Directional Drilling / Undergrounding Complete Remaining Miscellaneous Punch […]

Traffic impacts below for the week of 04/20/2026 for Phases 6N, 7N, 4S, 5S, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Punch List – Verify Completion Of Punch List – No Traffic Impacts PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders / Easement PHASE 4 SOUTH Horizontal Directional Drilling / Undergrounding  […]

Traffic impacts below for the week of 04/13/2026 for Phases 6N, 7N, 4S, 5S, 6S, 7S, 8, and the Cocoanut Row Watermain.  

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Punch List – Verify Completion Of Punch List – No Traffic Impacts PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders PHASE 4 SOUTH Horizontal Directional Drilling / Undergrounding  Complete Remaining […]

Traffic impacts below for the week of 04/06/2026 for Phases 6N, 7N, 4S, 5S, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Punch List – Verify Completion Of Punch List – No Traffic Impacts PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders PHASE 4 SOUTH Horizontal Directional Drilling / Undergrounding  Complete Miscellaneous Punch […]

Traffic impacts below for the week of 03/30/2026 for Phases 6N, 7N, 4S, 5S, 6S, 7S, 8, and the Cocoanut Row Watermain

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Punch List – Verify Completion Of Punch List – No Traffic Impacts PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders PHASE 4 SOUTH Horizontal Directional Drilling / Undergrounding  Complete Miscellaneous Punch […]

Traffic impacts below for the week of 03/23/2026 for Phases 6N, 7N, 4S, 5S, 6S, 7S, and Phase 8.

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Punch List – Verify Completion Of Punch List – No Traffic Impacts PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders PHASE 4 SOUTH Horizontal Directional Drilling / Undergrounding  […]

Traffic impacts below for the week of 03/16/2026 for Phases 6N, 7N, 4S, 5S, 6S, 7S, and Phase 8.

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Punch List – Verify Completion Of Punch List – No Traffic Impacts PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders PHASE 4 SOUTH Horizontal Directional Drilling / Undergrounding  […]

The traffic impacts below for the week of 03/09/2026 for Phases 6N, 7N, 4S, 5S, 6S, 7S, and Phase 8.

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Punch List – Verify Completion Of Punch List – No Traffic Impacts PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders PHASE 4 SOUTH Horizontal Directional Drilling / Undergrounding  […]

Traffic impacts below for the week of 03/02/2026 for Phases 6N, 7N, 4S, 5S, 6S, 7S, and Phase 8.

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Punch List – Replace FPL Feeder Box Lid – Not Scheduled This Week PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Equipment & Conduit Installation – FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders PHASE 4 […]

Traffic impacts for the week of 02/23/2026 for Phases  6N, 7N,4S, 5S, 6S, 7S, and Phase 8.

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Punch List – Replace FPL Feeder Box Lid – Not Scheduled This Week PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Equipment & Conduit Installation – FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders PHASE 4 […]