Traffic impacts below for the week of 11/30/2026 for Phases 6S, 7N, 7S, 8, and the Cocoanut Row Watermain Projects.
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
OH Wreck Out – (Monday Through Wednesday) – Pole & Wire Removal On North Ocean – ROAD CLOSED LOCAL TRAFFIC ONLY
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Remove / Replace Concrete Near 149 Clarke Ave.
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
Testing of FPL Feeder Cable – Various Locations – No Traffic Impacts
Connections To Transformers & Switches – Various Locations – No traffic impacts
General Clean-Up In Various Locations Throughout The Project – No Traffic Impacts
PHASE 8
Horizontal Directional Drilling / Undergrounding
HDD mainline conduits in easement Near 109 Atlantic / 240 N. Ocean– Lane Closures will be implemented – Traffic Maintained
HDD Mainline conduits on Everglade Ave between Bradley Place and N. County Road – Lane Closures will be implemented – Traffic Maintained
HDD Services – Oleander Ave working east to west – Lane Closures will be implemented – Traffic Maintained
Tie In Conduits – Atlantic Ave between N. County Road and N. Ocean – Lane Closures will be implemented – Traffic Maintained
Tie In Conduits On Seminole Between Bradley Place and N. County Road – Lane Closures will be implemented – Traffic Maintained
COCOANUT ROW WATERMAIN
Miscellaneous Punch List Items – No Traffic Impacts
**All Projects Subject To Change**