Lane Closure

TRAFFIC IMPACTS WEEK OF 03/07/2022

Below are the traffic impacts for the week of 3/07/2022 for the Phase 4 North,  Phase 5 North, Phase 2 South, Phase 3 South, and Phase 4 South projects.

PHASE 4 NORTH  

Horizontal Directional Drilling / Undergrounding

North Ocean Blvd.–Pulling strings & pulling feeder wire between La Puerta & Via Marila. Lane closure to be implemented. Traffic maintained.

Northlake Way–Pulling Strings in feeder conduits between El Pueblo & Orange Grove Road. Lane closure to be implemented. Traffic maintained.

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

Hi Mount Road–HDD. Traffic Maintained.

Ridgeview Road–HDD from North County to Northlake Way. Lane closure to be implemented. Traffic maintained.

PHASE 2 SOUTH 

Horizontal Directional Drilling / Undergrounding 

Miscellaneous transformer energizing dependent on switching orders from FPL.

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding 

HDD — Services on Jungle Road & El Vedado

HDD — S. County Road from El Vedado to Island

Conduit connections, equipment installation, road restoration — Jungle Road and S. County Road from Banyan Road north to El Vedado Road.

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD — Peruvian Avenue between South County Road and South Ocean Boulevard “LOCAL TRAFFIC ONLY”.