Lane Closure

Traffic Impacts Week of 04/11/2022

Below are the traffic impacts for the week of 4/11/2022 for the Phase 4 North, Phase 5 North, Phase 2 South, Phase 3 South, Phase 4 South, and Phase 5 South projects.

PHASE 4 NORTH  

Horizontal Directional Drilling / Undergrounding

NORTHLAKE WAY DETOUR– NLW to be closed between Via Marila and Orange Grove during working hours.  Tree and vegetation removal along with HDD at the D-10 Pump Station.

FPL equipment & wire terminations at various locations.  No anticipated traffic impacts.

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

Ridgeview Road–Conduit connections & equipment setting .Traffic maintained.

El Dorado Lane–HDD between N. County Road to Northlake Way. Lane closure to be implemented. Traffic maintained.

Northlake Way / Slope Trail–HDD between El Dorado Lane and Country Club Road. Lane closure to be implemented. Traffic maintained.

PHASE 2 SOUTH 

Horizontal Directional Drilling / Undergrounding 

Miscellaneous transformer energizing and conversions dependent on switching orders from FPL.

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding 

HDD — Private side services on El Brillo Way and El Bravo Way

Conduit connections, equipment installation, road restoration — El Vedado, and S. County Road from Jungle Road north to El Brillo Way.

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD — Peruvian Avenue in rear lot easements between South County Road and South Ocean Blvd.**There may be equipment parked on Chilean Ave. to perform the work**

HDD — Peruvian Avenue between South County & Hibiscus.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD — Chilean Avenue between South Lake Drive & Cocoanut Row then continuing east towards Hibiscus Ave.

“LOCAL TRAFFIC ONLY”