Lane Closure

­Traffic Impacts for the Week of 04/08/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 4 NORTH

FPL – Pole Removal (8 Each)  Via Crane on Monterey – “Road Closed Local Traffic Only”

PHASE 5 NORTH

Horizontal Directional Drilling / Undergrounding

HDD (COMCAST) – Northlake Way Between Via Linda & Polmer Park Road – Lane Closure To Be Implemented – Traffic Maintained

North Ocean – PBCC Parking Area – Section of South End Of Parking Area Along the West Side Of North Ocean To Be Blocked Off To Complete Switch Terminations – Pending FPL Switching Orders

Private Side Service Conversions – Various Locations – Awaiting FPL Switching Orders

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Terminations – Various Locations – No Traffic Impacts – Traffic Maintained

Curb Removal & Replacement – Various Locations – No Traffic Impacts – Traffic Maintained

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – Alley Between Sandpiper & Eden From Northlake Way To North Ocean –  “Road Closed” – No Through Traffic

HDD – Jamaica Lane Between Northlake Way & North Ocean – “Road Closed Local Traffic Only” – Traffic Maintained

Equipment & Conduit Installation – Jamaica Lane Between Northlake Way & North Ocean Blvd. –  “Road Closed Local Traffic Only” – Traffic Maintained

Equipment & Conduit Installation – Alley Between Sandpiper & Eden From Northlake Way To North Ocean –  “Road Closed” – No Through Traffic

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Continue conversions and remaining switching orders as they are released by FPL.

HDD – Island Drive – (FPL Work)

Conduit connections, equipment installation, and road restorations on Island Drive.

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Cable Installation Throughout The Phase 

Device Installation and Terminations Throughout The Phase

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Switching orders as they are released by FPL. Continue conversions as allowable.
Sidewalk restorations on Cocoanut Row and Seaview Avenue.

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Conduit connections, equipment installation, and road restorations on Seabreeze Avenue between South County Road and the intracoastal and in the Clarke Alleyway from South County Road to South Ocean Boulevard.

“LOCAL TRAFFIC ONLY” 

**All Phases Subject to Change**