Traffic Impacts for the Week of 08/19/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Service Conversions as released by FPL – Various Locations – No Traffic Impacts – Traffic Maintained
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Conversions As Released By FPL – Various Locations – No Traffic Impacts – Traffic Maintained
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – Northlake Way From Tradewinds North To Via Marila Road – Lane Closure To Be Implemented – Traffic Maintained
HDD – Sandpiper Drive – North Ocean Blvd. To Northlake Way – “Road Closed” Local Traffic Only – Traffic Maintained
HDD (Services) – N. Lake Way between Via Marila & Garden – “ROAD CLOSED” – Detour to be implemented (Aug 19th & 20th) Traffic will be maintained on all intersecting streets.
Wire Pulling – Tradewinds Between Northlake Way & North Ocean Blvd. – No Traffic Impacts
Equipment & Conduit Installation – Sandpiper Between Northlake Way and North Ocean Blvd. – “Road Closed” Local Traffic Only – Traffic Maintained
Equipment & Conduit Installation – Northlake Way From Tradewinds To Via Marila – Lane Closure To Be Implemented – Traffic Maintained
PHASE 2 SOUTH
Curb Work At 123 Kings Road
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue conversions and remaining switching orders as they are released by FPL.
Remove & Replace Sidewalk Near Everglades Club. Curb Work at 209 Banyan.
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Terminations Throughout The Phase. Switching Orders As They Are Released By FPL.
Miscellaneous Sidewalk & Curb Installation Throughout The Phase
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Switching orders as they are released by FPL. Continue conversions as allowable.
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Conduit connections, equipment installation, and road restoration on Royal Poinciana Way From Cocoanut Row To South County Road. Cocoanut Row From Seabreeze to White Hall. Breakers Golf Course at South County & Main Street, Pendelton from South Lake Trail To South Ocean and miscellaneous locations on Primavera & Antigua Lane.
Other Traffic Impacts
HOTWIRE WORK UNRELATED TO TOPB UNDERGROUNDING
HDD on N. County Road Between Flagler Steakhouse & Root Trail
HDD on Root Trail from N. County Road to N. Ocean Blvd.
HDD on Sunset Ave from N. County Road to Northlake Trail
***Any Questions Pertaining to this work are to be directed to HOTWIRE or WILCO ELECTRICAL***
“LOCAL TRAFFIC ONLY”
**All Phases Subject to Change**