Traffic Impacts for the Week of 11/18/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and Phase 6 South Projects
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Conversions – Various Locations – No Traffic Impacts – Traffic Maintained . Pending FPL’s Release of Switching Orders
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Conversions – Various Locations – No Traffic Impacts – Traffic Maintained. Pending FPL’s Release of Switching Orders
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – Laurian Lane – North Ocean To Northlake Way – “Road Closed” Local Traffic Only – Traffic Maintained
HDD – North Alley (South of Garden Road) – Northlake Way to North Ocean – “Road Closed” Local Traffic Only – Traffic Maintained
Equipment & Conduit Installation – Via Marila Between Northlake Way and N. Ocean -“Road Closed” Local Traffic Only – Traffic Maintained
Equipment & Conduit Installation – North Alley Between Northlake Way & North Ocean – “Road Closed”
Wire Pulling (Primary) – Via Marilia Between Northlake Way & North Ocean Blvd. – “Road Closed” Local Traffic Only – Traffic Maintained”
PHASE 2 SOUTH
No Anticipated Work
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue Misc. Concrete Work – Bollard Installation – Punch List Items – Throughout The Phase
Continue Remaining Prep Work On Golfview Alley
Complete Final Conversions and Switching Orders on Island Way and Vita Serena.
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Additional Switching Orders That Were Released
Continue Misc. Concrete Work – Bollard Installation – Punch List Items – Mainly Off Peruvian In Rear Lots & Easements
Complete Make Up & termination Work Throughout The Phase
Plan / Coordinate Outage For 375 South County Road Vault Work
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Misc. Punch List Items Throughout The Phase
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Cable Pulling Throughout The Phase – Coordinating With Breakers With Work On S. County Road. (Only after Cocoanut Opens and no drainage work on Cocoanut is scheduled)
Equipment Installation Throughout the Phase As Received From FPL
Conduit Connections, Equipment Installation, and Road Restoration on Royal Poinciana Way from Cocoanut To South County Road, Cocoanut Row Between Seaview and Royal Poinciana Way, Pendleton west of Cocoanut Row, South County Road and Breakers Golf Course.
CLARKE ALLEY CLOSURE – CLOSED TO ALL TRAFFIC – Cocoanut Row To County Road – Drainage Work To Continue. Approved Traffic Plan To Be Implemented.
COCOANUT ROW CLOSURE – CLOSED TO ALL TRAFFIC – COCOANUT ROW TO BE CLOSED BETWEEN SEABREEZE AVENUE AND CLARKE AVENUE TO INSTALL A STORM DRAINAGE LINE – APPROVED DETOUR TO BE IMPLEMENTED
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**