Lane Closure

­Traffic Impacts for the Week of 3/24/2025 for the Phase 5, 6, & 7 North, as well as Phase 3, 4, 5, 6 & 7 South Projects

PHASE 5 NORTH 

Horizontal Directional Drilling / Undergrounding

FPL & ATT Overhead Line Removal – Various Locations

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Punch List – Various Locations – No Traffic Impacts

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

Wire Pulling (Feeder)  – Northlake Way Between Bahama & Via Marila, Bahama Between Northlake Way & North Ocean, North Ocean Between Bahama & Via Marila. – Lane Closure To Be Implemented – Traffic Maintained

Feeder Splicing – Various Locations – No Traffic Impacts

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Continue With Overhead Wreck Out , Wire & Equipment Removal – East/West Streets – Intracoastal To South Ocean – South End Working North – Flagging Operation To Be Implemented

Via Marina & South County Road – Concrete Replacement Pending Concrete Availability

Golfview Alley – Complete Feeder Switching Order Pending FPL Release

Golfview Alley – Fence & Gate Repair/Replacement – Awaiting Fabrication

Bollard Installation – Various Locations

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Continue With Conversions

Continue With Streetlight / Traffic Signal Power & Controller Installations

Complete Make Up & Termination Work Throughout The Phase

Feeder Drop Near West Side of Cocoanut & Chilean. Monday 3/24 & Tuesday 3/25. Some Parking Spaces Will Be Occupied.

Manhole Work – Peruvian Ave. Just West Of South Ocean Near The SW Corner Of 400 South Ocean Including Work In The Manhole At West Side of 400 South Ocean.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

No Work Anticipated

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Continue Make Up & Termination Work Throughout The Phase

Continue HDD, TIe-Ins & Equipment Setting on Pendleton 

PHASE 7 SOUTH

HDD Drilling (Mainline) – Crescent Drive Between North County Road & Wells Road  – Road Closed – Local Traffic Only – Traffic Maintained

HDD Drilling (Mainline) – Emerald Lane Between Northlake Way and Crescent Drive –  Road Closed – Local Traffic Only – Traffic Maintained

Conduit and Equipment Installation – Sanford Avenue Between Northlake Way & North County Road – Road Closed – Local Traffic Only – Traffic Maintained

Conduit and Equipment Installation – Emerald Lane Between Northlake Way & Crescent Drive – Road Closed – Local Traffic Only – Traffic Maintained

“LOCAL TRAFFIC ONLY” 

**All Phases Subject To Change**