Traffic Impacts for the Week of 4/14/2025 for the Phase 5, 6, & 7 North, as well as Phase 3, 4, 5, 6 & 7 South Projects
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
FPL Overhead Line / Equipment Removal – Various Locations
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List – Various Locations – No Traffic Impacts
FPL Feeder Riser Drop – Northlake Way – Pending FPL Release of Order.
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Feeder Splicing – Various Locations – No Traffic Impacts
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue With Overhead Wreck Out , Wire & Equipment Removal – East/West Streets – Intracoastal To South Ocean – South End (El Brillo Way) Working North – Flagging Operation To Be Implemented
Golfview Alley – Fence & Gate Repair/Replacement – 4/14/25 & 4/15/25
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Conversion Work Throughout The Phase
Manhole Work & Switching Order – Vista Switch – 355 South Ocean – Pending FPL Release of Switching Order.
Final Prep Work for Riser Drops – Various Locations – Traffic Maintained
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Seaview Chicane Curb Rework – Pending Concrete Availability – Traffic Maintained
Sidewalk Repair – 434 Chilean Ave – Traffic Maintained
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue Make Up & Termination Work Throughout The Phase
Complete Work For Primary Meter Cabinet Installation – Breakers Golf Course – Pending FPL Material
Complete Terminations at 3 Transformers on Cocoanut – Traffic Maintained
Curb Work At Newly Installed Transformers – Various Locations – Seabreeze Avenue
PHASE 7 SOUTH
HDD Drilling (Mainline) – Wells Road Between Northlake Way and Crescent Drive – Road Closed – Local Traffic Only – Traffic Maintained
HDD Drilling (Mainline) – North County Road (West Side) – Wells To Sanford – Bike Path To Close – Pedestrian Traffic Maintained
Conduit and Equipment Installation – Sanford Avenue Between Northlake Way & North County Road – Road Closed – Local Traffic Only – Traffic Maintained
Conduit and Equipment Installation – Emerald Lane Between Northlake Way & Crescent Drive – Road Closed – Local Traffic Only – Traffic Maintained
Conduit and Equipment Installation – Crescent Road Between Emerald and Wells Road – Road Closed – Local Traffic Only – Traffic Maintained
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**