Traffic Impacts for the Week of 7/14/2025 for the Phase 5, 6, & 7 North, Phase 3, 4, 5, 6, 7 South, Phase 8 and Clarke Alley Projects
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
FPL Pole Removal – Various Locations
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List – Install Top Soil & Sod Behind Poured Curbs – Various Locations – No Traffic Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Switching Orders As Received From FPL – Various Locations
Residential Conversions – Various Locations – No Traffic Impacts
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
OH Crews To Continue Straggler Pole Removal – Various Locations – El Brillo, El Bravo, & El Vedado West of County. (Monday – Thursday).
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Begin Conversion Prep Work At Peruvian Lot For Conversions at 309,323,325, & 341 Worth.
Continue Switching Orders & Splicing Two Manholes and Condo Vault Rooms on S. Ocean Blvd.
359 S. County Rd. Meter Bank Swap Out. – No traffic impacts.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Punch-list Items Generated From Walkthrough. – No traffic impacts
Concrete Restoration Work – West End Of Seabreeze at the Cul-De-Sac, SW Corner of Seabreeze & Cocoanut, & 400 Royal Palm Way in parking lot
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Execute Switching Orders As They’re Received From FPL – Various Locations – No Traffic Impacts.
Continue With Conversions & Conversion Prep Work
Concrete Restoration Along Royal Poinciana, East Main, & N. Breaker Row.
Frame Out Make Ready Riser On N. County Between Sunset & E. Main Street. (Wednesday & Thursday)
PHASE 7 SOUTH
HDD Drilling (Mainline) – N. County Road From Wells Road To Atlantic Ave. – Lane Closure To Be Implemented – Traffic Maintained
Conduit Installation – Coral Lane Between N. Lake Way & Crescent Road – “ROAD CLOSED” Local Traffic Only – Traffic Maintained
Conduit & Equipment Installation – North County Road Between Wells Road And Atlantic Ave. – Lane Closure To Be Implemented – Traffic Maintained
Equipment installation – Dunbar Between North Ocean And Bradley – Road Closed – Local Traffic Only – Traffic Maintained
PHASE 8
Horizontal Directional Drilling / Undergrounding
HDD On Bradley Place Between Oleander And Everglade Ave – Single Lane Closures/Shifts – Traffic Maintained. (Monday – Tuesday)
HDD On Seminole – West Of Bradley To Lake Trail- Road Closed – Local Traffic Only – Traffic Maintained (Wednesday – Thursday)
Tie In Crew On Bradley Place Between Sunset Ave and Sunrise Ave. North Bound Traffic To Detour On To Sunset To Be Implemented Pending Approval. (Monday – Tuesday)
Tie In Crew On Sunset West of Bradley at 333 Sunset (Wednesday – Thursday)
CLARKE ALLEY
CLARKE ALLEY CLOSED FOR ALLEY RECONSTRUCTION – DETOUR IMPLEMENTED
Roadway Reconstruction – Subgrade Prep . & Base Rock Installation
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**