Traffic Impacts for the Week of 07/28/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8, and Clarke Alley
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List – Install Topsoil & Sod Behind Poured Curbs – Various Locations – No Traffic Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Residential Conversions – Various Locations – No Traffic Impacts
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue Work at Peruvian Lot for Conversions at 323,325, & 341 Worth.
Continue Switching Orders for Vault & Manhole Work on S. Ocean Blvd.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Punch-list Items Generated from Walkthrough. – No traffic impacts
Concrete Restoration Work – 318 & 319 Seaspray (Need to Confirm Concrete Delivery Schedule)
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Execute Switching Orders as They’re Received from FPL – Various Locations – No Traffic Impacts.
Continue With Conversions & Conversion Prep Work
Concrete Restoration Along Royal Poinciana Near Breaker Parking Lot Entrance, South County Road just south of Royal Poinciana Road. (Need To Confirm Concrete Delivery Schedule)
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling (Mainline) – N. County Road from Wells Road to Atlantic Ave. – Lane Closure to Be Implemented – Traffic Maintained
HDD Drilling (Mainline & Services) – Canterbury Lane Between North County Road and the East End of Canterbury. Road Closed – Local Traffic Only – Traffic Maintained.
Conduit & Equipment Installation – North County Road Between Wells Road and Atlantic Ave. – Lane Closure to Be Implemented – Traffic Maintained
Conduit & Equipment Installation – Canterbury Lane & The Cul-De-Sac – “ROAD CLOSED” Local Traffic Only – Traffic Maintained
PHASE 8
Horizontal Directional Drilling / Undergrounding
HDD On Seminole Between Bradley and North County- Lane Closure to Be Implemented – Traffic Maintained
HDD On Oleander Between Bradley and County – Road Closed – Local Traffic Only – Traffic Maintained
Tie In Crew on Bradley Place Between Sunrise & Sunset. Lane Closure to Be Implemented – Traffic Maintained
CLARKE ALLEY
CLARKE ALLEY CLOSED FOR ALLEY RECONSTRUCTION – DETOUR IMPLEMENTED
Roadway Reconstruction – Subgrade Prep . & Base Rock Installation
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**