Traffic Impacts for the Week of 08/04/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8, and Clarke Alley
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Finalize Punch List – Various Locations – No Traffic Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Residential Conversions – Various Locations – No Traffic Impacts
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue Work At Peruvian Lot For Conversions at 323,325, & 341 Worth Ave.
Continue Remaining Switching Orders For Vault & Manhole Work.
Continue With Wall Mounted Prep Work At 290 S. County Road.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Punch-list Items Generated From Walkthrough. – No traffic impacts.
Overhead Wreck Out – PB Day Academy & Pole Line Between Seaspray & Seaview (Rear Lot Easement). Crane Set Up Is Dependent On Pole Being Removed.
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Execute Switching Orders As Received From FPL – Various Locations – No Traffic Impacts.
Continue With Conversions & Conversion Prep Work
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling (Mainline) – N. County Road From Wells Road To Atlantic Ave. – Lane Closure To Be Implemented – Traffic Maintained
HDD Drilling (Mainline & Services) – Canterbury Lane Between North County Road and the East End Of Canterbury. Road Closed – Local Traffic Only – Traffic Maintained.
Conduit & Equipment Installation – North County Road Between Wells Road And Atlantic Ave. – Lane Closure To Be Implemented – Traffic Maintained
Conduit & Equipment Installation – Canterbury Lane & The Cul-De-Sac – “ROAD CLOSED” Local Traffic Only – Traffic Maintained
PHASE 8
Horizontal Directional Drilling / Undergrounding
HDD On Seminole Between Bradley And North County- Lane Closure To Be Implemented – Traffic Maintained
HDD On Oleander Between Bradley And County – Road Closed – Local Traffic Only – Traffic Maintained
Tie In Crew On Bradley Place Between Sunrise & Sunset. Lane Closure To Be Implemented – Traffic Maintained
CLARKE ALLEY
CLARKE ALLEY CLOSED FOR ALLEY RECONSTRUCTION – DETOUR IMPLEMENTED
Roadway Reconstruction – Subgrade Prep . & Base Rock Installation
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**