Lane Closure

Traffic impacts for the week of 08/11/2025 for Phases 6N, 7N, 3S,4S, 5S, 6S, 7S, Phase 8, and Clarke Alley

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Finalize Punch List – Various Locations – No Traffic Impacts

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

Residential Conversions – Various Locations – No Traffic Impacts

PHASE 3 SOUTH

Concrete Curb – Golfview Road At Corner South Of Everglades Club

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Continue Work At Peruvian Lot For Conversions at 325, & 341 Worth.

Concrete Curb Work In Parking Lot At 354 Chilean

Continue With Wall Mounted Prep Work At 290 S. County Road

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Complete Punch-list Items Generated From Walkthrough. – No traffic impacts

OH Wreck Out – Pole Line Between Seaspray & Seaview (Rear Lot Easement). Crane Set Up Is Dependent On Pole Being Removed.

Concrete Curb Work At 319 & 322 Seaspray

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Execute Switching Orders As They’re Received From FPL – Various Locations – No Traffic Impacts.

Continue With Conversions & Conversion Prep Work

Continue With Concrete Restoration Work Various Locations

PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD Drilling (Mainline) – N. County Road From Wells Road To Atlantic Ave. – Lane Closure To Be Implemented – Traffic Maintained

HDD Drilling (Mainline & Services) – Everglade Ave From Bradley To The Intracoastal – Road Closed – Local Traffic Only – Traffic Maintained.

HDD Drilling (Mainline) -Bradley Place Between Everglade Ave And Dunbar – Lane Closure To Be Implemented – Traffic Maintained

HDD Drilling (Mainline & Services) – Canterbury Lane Between North County Road and the East End Of Canterbury. Road Closed – Local Traffic Only – Traffic Maintained.

Conduit & Equipment Installation – North County Road Between Wells Road And Atlantic Ave. – Lane Closure To Be Implemented – Traffic Maintained

Conduit & Equipment Installation – Canterbury Lane & The Cul-De-Sac – “ROAD CLOSED” Local Traffic Only – Traffic Maintained

PHASE 8

Horizontal Directional Drilling / Undergrounding

HDD On North County From Atlantic Heading South In Southbound Lane- Lane Closure To Be Implemented – Traffic Maintained

HDD On Oleander Between Bradley And County – Road Closed – Local Traffic Only – Traffic Maintained 

Tie In Crew On Bradley Place Between Sunrise & Park. Lane Closure To Be Implemented – Traffic Maintained

CLARKE ALLEY