Traffic impacts for the week of 09/01/2025 for Phases 6N, 7N, 3S,4S, 5S, 6S, 7S, Phase 8, and Clarke Alley
~Monday September 1st is Labor Day, there is no work permitted on this day~
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Finalize Punch List – Various Locations – No Traffic Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Residential Conversions – Various Locations – No Traffic Impacts
PHASE 3 SOUTH
No work scheduled.
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Final prep for conversion using wall mounted conduit at 290 S. County Rd. (TUE)
Conversion at 290 SCR (WED) – No Traffic Impacts
Begin Overhead Wreckout and Pole Removal, pending execution of FPL switching order(s)
***SEE ATTACHED MOT PLANS BELOW FOR ANTICIPATED DETOURS, DETOURS SUBJECT TO CHANGE BASED ON EXISTING POLE CONDITIONS AND CRANE SETUP
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Overhead crew – wreck out pole line between Seaspray & Seaview, work west of Cocoanut, set up on Seaspray west end (Tue-Thur)
Overhead crew – wreck out area surrounding 4 Arts Plaza (Fri)
Overhead crew – wreck out pole line between Brazilian
***SEE ATTACHED MOT PLANS BELOW FOR ANTICIPATED DETOURS, DETOURS SUBJECT TO CHANGE BASED ON EXISTING POLE CONDITIONS AND CRANE SETUP
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Prep and execute SO’s as they become available – No Traffic Impacts
Continue with conversions. – No Traffic Impacts
Continue with concrete restoration work. – No Traffic Impacts
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling (Mainline & Services) – Canterbury Lane Between North County Road and the East End Of Canterbury. Road Closed – Local Traffic Only – Traffic Maintained.
HDD Drilling (Mainline & Services) – Bradley Place between Everglade Ave & Wells Road – One lane closure to be implemented – Traffic Maintained.
Conduit & Equipment Installation – Canterbury Lane & The Cul-De-Sac – “ROAD CLOSED” Local Traffic Only
Conduit & Equipment Installation – Bradley Place between EVERGLADE AVE & Wells Road – Lane Closure to be implemented – Traffic Maintained.
PHASE 8
Horizontal Directional Drilling / Undergrounding
HDD on N County Rd. working from Everglade south in SB lane. – Traffic Maintained
HDD on Oleander between Bradley PL and N County – Traffic Maintained
HDD on Park Ave between Bradley PL and N County – Traffic Maintained
Tie-In crew working on Bradley PL between Sunset and Everglade. – Traffic Maintained
Tie-In crew working on switches at NE corner of Park and Bradley (150 Bradley PL). – Traffic Maintained
CLARKE ALLEY
CLARKE ALLEY CLOSED FOR ALLEY RECONSTRUCTION – DETOUR IMPLEMENTED
Roadway Reconstruction – Subgrade Prep, Base Rock Installation, Pouring Concrete
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**