Lane Closure

Traffic Impacts for the week of 10/06/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8, and Clarke Alley

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Finalize Punch List – Various Locations

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

Residential Conversions as FPL Releases Final Orders – Various Locations 

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Overhead Wreckout and Pole Removal. The Area will encompass Brazilian Ave., Chilean Ave., and Hibiscus Ave., to County Road.

“Detour To Be Implemented” – Rolling Closure

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

No Work Anticipated

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Barton Avenue East of Cocoanut – Lane Closure – Traffic Maintained

HDD on Cocoanut Row Between Clarke Alley and Whitehall Way – Lane Closure – Traffic Maintained

HDD on Pendleton – Lane Closure – Traffic Maintained

Prep and execute SO’s as they become available – Various Locations

Continue with conversions. – Various Locations

Tie In Crew On S. Lake Trail Between Seabreeze and Antigua Lane.

PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD Drilling (Mainline & Services) – Intersection of Atlantic & Dunbar Between Bradley Place & the Intra-Costal. Road Closed – Local Traffic Only – Traffic Maintained.

HDD Drilling (Mainline & Services) – Bradley Place between Everglade Ave & Wells Road – One lane closure to be implemented – Traffic Maintained.

Conduit & Equipment Installation – Intersection of Bradley Place & Atlantic Ave., Bradley Place, & Dunbar – Lane Closure to be implemented – Traffic Maintained.

PHASE 8

Horizontal Directional Drilling / Undergrounding

Tie-In Crew Working on Bradley PL between Sunset and Everglade. – Lane Closure – Traffic Maintained

CLARKE ALLEY

“LOCAL TRAFFIC ONLY” 

**All Phases Subject To Change**