Lane Closure

Traffic Impacts for the week of 10/13/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8, and Clarke Alley

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Punch List Complete – Schedule Walk Through – No Impacts 

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

Residential Conversions As FPL Releases Final Orders – Various Locations 

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Overhead Wreckout and Pole Removal Along Brazilian Ave. Working West to East, From Hibiscus Ave. to S. Ocean

Overhead Wreckout and Pole Removal Along Hibiscus Avenue from Royal Palm Way to Peruvian

Overhead Wreckout and Pole Removal Along Chilean from Hibiscus and S. County

Complete Miscellaneous Punch List Items

“Detours To Be Implemented” – Rolling Closures for Pole Removals

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Overhead Wreckout along Cocoanut Row Between Royal Palm Way and Seaspray. (Saturday 10/17/2025)

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Cocoanut Row Between Clarke Alley and Whitehall Way – Lane Closure – Traffic Maintained

HDD on Via Sunny (Will Coordinate with Homeowners) 

HDD on Pendleton – Lane Closure – Traffic Maintained

HDD on Barton Ave East of Cocoanut Row – Lane Closure – Traffic Maintained

Prep and execute Switching Orders as they become available – Various Locations

Continue with conversions. – Various Locations

Tie In Crew on S. Lake Trail Between Seabreeze and Antigua Lane.

N. County Road – Execute Switching Orders – Breakers Row to Royal Poinciana – North Bound Lane Closure – Traffic Maintained

PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD Drilling (Mainline & Services) – Bradley Place between Dunbar Ave & Wells Road – One lane closure to be implemented – Traffic Maintained.

Conduit & Equipment Installation – Intersection of Bradley Place & Dunbar – Lane Closure to be implemented – Traffic Maintained.

Conduit & Equipment Installation – Intersection of Bradley Place & Wells Road – Lane Closure to be implemented – Traffic Maintained.

PHASE 8

Horizontal Directional Drilling / Undergrounding

No Work Scheduled – No Traffic Impacts

CLARKE ALLEY

“LOCAL TRAFFIC ONLY” 

**All Phases Subject To Change**