Lane Closure

Traffic Impacts for the week of 11/24/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Punch List – Replace FPL Feeder Box Lid When Supplied By FPL – No Impacts 

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

Lay Out / Sawcut Drill Pits and Trench Lines – Via Marila & Laurian Lane between North Lake Way and North Ocean. Alley Between Garden and Eden – No Traffic Impacts

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Misc. Concrete Work Throughout The Area

Complete Miscellaneous Punch List Items

PHASE 5 SOUTH


Horizontal Directional Drilling / Undergrounding


Work on miscellaneous punch list items – No Traffic Impacts

Misc. Concrete Work Throughout The Area

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Tie In Crews on Pendleton and Barton Between Cocoanut & S. County Road.

Tie In Crew on Via Bethesda and Barton Ave Between S. County Road & Flagler Drive.

Prep and execute SO’s as they become available – Various Locations

Continue with conversions. – Various Locations


PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD Drilling (Mainline) – Northlake Way Between Wells Road & Emerald –  Lane Closure To Be Implemented – Traffic Maintained

Conduit & Equipment Installation – Dunbar Between Bradley Place & North County Road – No Traffic Impacts

Conduit & Equipment Installation – Northlake Way Between Bradley Place & N. County Road – Lane Closure To Be Implemented – Traffic Maintained

Wire Pulling – Various Locations – No Traffic Impacts

PHASE 8

Horizontal Directional Drilling / Undergrounding

No Work Scheduled – No Traffic Impacts

“LOCAL TRAFFIC ONLY” 

**All Phases Subject To Change**