Traffic Impacts for the week of 11/24/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8
**THERE WILL BE NO WORK ON THURSDAY 11/27/2025 AND FRIDAY 11/28/2025 IN OBSERVANCE OF THANKSGIVING**
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List – Replace FPL Feeder Box Lid When Supplied By FPL – No Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Lay Out / Sawcut Drill Pits and Trench Lines – Via Marila & Laurian Lane between North Lake Way and North Ocean. Alley Between Garden and Eden – No Traffic Impacts
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Misc. Concrete Work Throughout The Area
Complete Miscellaneous Punch List Items
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Work on miscellaneous punch list items – No Traffic Impacts
Misc. Concrete Work Throughout The Area
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Tie In Crews on Pendleton and Barton Between Cocoanut & S. County Road.
Tie In Crew on Via Bethesda and Barton Ave Between S. County Road & Flagler Drive.
Prep and execute SO’s as they become available – Various Locations
Continue with conversions. – Various Locations
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling (Mainline) – Northlake Way Between Wells Road & Emerald – Lane Closure To Be Implemented – Traffic Maintained
Conduit & Equipment Installation – Dunbar Between Bradley Place & North County Road – No Traffic Impacts
Conduit & Equipment Installation – Northlake Way Between Bradley Place & N. County Road – Lane Closure To Be Implemented – Traffic Maintained
Wire Pulling – Various Locations – No Traffic Impacts
PHASE 8
Horizontal Directional Drilling / Undergrounding
No Work Scheduled – No Traffic Impacts
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**




