Lane Closure

Traffic Impacts for the Week of 12/08/2025 for Phases 6N, 7N,4S, 5S, 6S, 7S, and Phase 8

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Punch List – Replace FPL Feeder Box Lid When Supplied By FPL – No Impacts 

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

HDD Drilling (ATT & COMCAST) – North Ocean Between Via Marila & Tradewinds – South Bound Lane -Lane Closure To Be Implemented – Traffic Maintained

FPL Feeder Riser Drop – North Ocean at Boyd’s Park – Lane Closure To Be Implemented – Traffic Maintained

Conduit Installation – Alley Between Garden & Eden – “Road Closed” Local Traffic Only

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding 

Misc. Concrete Work Throughout The Area

Complete Miscellaneous Punch List Items  No Traffic Impacts

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Work on miscellaneous punch list items – No Traffic Impacts

Misc. Concrete Work Throughout The Area

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Tie In Crew on Barton Ave, Clarke Alley, and Flagler Drive East of S. County Road.

Prep and Execute SO’s as they become available – Various Locations

Continue with conversions. – Various Locations

Street Light Controllers & Traffic Signal Breaker Installation – No Traffic Impacts

PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD Drilling (Mainline) – Northlake Way Between Wells Road & Coral –  Lane Closure To Be Implemented – Traffic Maintained

HDD Drilling (Mainline) – Atlantic Road At The Intersection Of N. County Road & Atlantic – No Traffic Impacts – Traffic Maintained

Conduit & Equipment Installation – Northlake Way Between Wells Road & Emerald Lane – Lane Closure To Be Implemented – Traffic Maintained

Wire Pulling – Various Locations – No Traffic Impacts

PHASE 8

Horizontal Directional Drilling / Undergrounding

No Work Scheduled – No Traffic Impacts

**All Phases Subject To Change*