Traffic impacts for the week of 12/22/2025 for Phases 6N, 7N,4S, 5S, 6S, 7S, and Phase 8.
**NO WORK DECEMBER 24TH OR 25TH IN OBSERVANCE OF THE CHRISTMAS HOILDAY**
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
No Work Scheduled – Closed For Vacation – Returning 01-05-2026
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
No Work Scheduled – Closed For Vacation – Returning 01-05-2026
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Miscellaneous Punch List Items No Traffic Impacts
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Work on miscellaneous punch list items – No Traffic Impacts
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Prep and Execute SO’s as they become available – Various Locations
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
No Work Scheduled – Closed For Vacation – Returning 01-05-2026
PHASE 8
Horizontal Directional Drilling / Undergrounding
No Work Scheduled – No Traffic Impacts