Lane Closure

Traffic impacts for the week of 12/22/2025 for Phases 6N, 7N,4S, 5S, 6S, 7S, and Phase 8.

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

No Work Scheduled – Closed For Vacation – Returning 01-05-2026

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

No Work Scheduled – Closed For Vacation – Returning 01-05-2026

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding 

Complete Miscellaneous Punch List Items  No Traffic Impacts

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Work on miscellaneous punch list items – No Traffic Impacts

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Prep and Execute SO’s as they become available – Various Locations

PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

No Work Scheduled – Closed For Vacation – Returning 01-05-2026

PHASE 8

Horizontal Directional Drilling / Undergrounding

No Work Scheduled – No Traffic Impacts