Traffic impacts for the week of 01/19/2026 for Phases 6N, 7N,4S, 5S, 6S, 7S, and Phase 8.
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List – Replace FPL Feeder Box Lid – Awaiting FPL Delivery – No Traffic Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling – (AT&T) – Northlake Way From Via Marila & Bahama Lane – Lane Closure To Be Implemented – Traffic Maintained
Equipment & Conduit Installation – Alley Between Garden & Eden – “ROAD CLOSED” – Local Traffic Only – Traffic Maintained
Pulling Feeder – Northlake Way Between Bahama Lane & Via Marila – Lane Closure To Be Implemented – Traffic Maintained
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Miscellaneous Punch List Items No Traffic Impacts
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Work on miscellaneous punch list items – No Traffic Impacts
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Prep and Execute SO’s As They Become Available – Various Locations
Prep and Complete Any Remaining Conversions – No Traffic Impacts
Complete Installation Of Traffic Controller Breakers & Street Lighting Controls – No Traffic Impacts
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling – Atlantic Road Between N. County Road & Bradley Place – “ROAD CLOSED” – Local Traffic Only – Traffic Maintained
HDD Drilling – Northlake Way Between Wells Road & Sanford – Lane Closure To Be Implemented – Traffic Maintained
Equipment & Conduit Installation – Atlantic Ave Between Bradley Place & N. County Road – “ROAD CLOSED” – Local Traffic Only – Traffic Maintained
PHASE 8
Horizontal Directional Drilling / Undergrounding
No Work Scheduled – No Traffic Impacts **All Phases Subject To Change*