Lane Closure

Traffic impacts for the week of 02/02/2026 for Phases 6N, 7N,4S, 5S, 6S, 7S, and Phase 8.

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Punch List – Replace FPL Feeder Box Lid, pending completion of work in 7 North – No Traffic Impacts

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

HDD Drilling – (AT&T) – Northlake Way Between Via Marila & Bahama Lane – Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – Alley Between Garden & Eden – “ROAD CLOSED” – Local  Traffic Only – Traffic Maintained

Equipment & Conduit installation – N. Lake Way between VIA MARILA & Bahama Lane – Lane Closure to be implemented – Traffic Maintained

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding 

Complete Miscellaneous Punch List Items  No Traffic Impacts

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Work on miscellaneous punch list items – No Traffic Impacts

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Prep and execute SO’s as they become available.

Prep and complete any remaining conversions, no traffic impacts.

Complete installation of street lighting controls, no traffic impacts.

Install Breakers CT cabinet – Temporary Lane Closure to be implemented East side Northbound Lane.

PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD Drilling (ATT Fiber) – Crescent Drive between N. County Rd. & Wells Road – “ROAD CLOSED” – Local  Traffic Only – Traffic Maintained

Equipment & Conduit installation – N. Lake Way between Kawama & Wells Road – Lane Closure to be implemented – Traffic Maintained

PHASE 8

Horizontal Directional Drilling / Undergrounding

No Work Scheduled – No Traffic Impacts

**All Phases Subject To Change**