Lane Closure

Traffic impacts for the week of 02/09/2026 for Phases  6N, 7N,4S, 5S, 6S, 7S, and Phase 8.

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Punch List – Replace FPL Feeder Box Lid – Not Scheduled This Week

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

Equipment & Conduit Installation – Alley Between Garden & Eden – “ROAD CLOSED” – Local  Traffic Only – Traffic Maintained

Equipment & Conduit installation – NoN. Lake Way between VIA MARILA & Bahama Lane – Lane Closure to be implemented – Traffic Maintained

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding 

Complete Miscellaneous Punch List Items  No Traffic Impacts

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Work on miscellaneous punch list items – No Traffic Impacts

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Prep and execute SO’s as they become available.

Prep and complete any remaining conversions, no traffic impacts.

Complete installation of street lighting controls, no traffic impacts.

Install Breakers CT cabinet – Temporary Lane Closure to be implemented East side Northbound Lane. Sidewalk to also closed to pedestrians. Will coordinate the date once confirmed.

PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD Drilling (ATT Fiber) – Crescent Drive between N. County Rd. & Wells Road – “ROAD CLOSED” – Local  Traffic Only – Traffic Maintained

HDD Drilling – Atlantic Ave. Between Bradley Place & N. County Road – “ROAD CLOSED” – Local  Traffic Only – Traffic Maintained

Equipment & Conduit installation – N. Lake Way between Kawama & Wells Road – Lane Closure to be implemented – Traffic Maintained

PHASE 8

Horizontal Directional Drilling / Undergrounding

No Work Scheduled – No Traffic Impacts

**All Phases Subject To Change**