Traffic impacts below for the week of 08/03/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List items – Various Locations – No Traffic Impact
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Overhead Wreck Out – Pole & Wire Removal – North County Road – Via Bethesda to Royal Poinciana – Lane Closure – Traffic Maintained
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
Equipment & Conduit Installation – Relocated Transformer At 158 Dunbar – No Traffic Impacts
Install Service Conduits (Back Yards) – Various Locations – No Traffic Impacts
Primary & Secondary Wire Pulling – Various Locations – Traffic Maintained
PHASE 8
Horizontal Directional Drilling / Undergrounding
HDD on Sunset Ave between Bradley Place and N. County Road. – Traffic Maintained
HDD on N. County Rd. between Atlantic and Sunrise – Lane Closure to be implemented – Traffic Maintained.
HDD services on Root Trail between N. County and N. Ocean – Road Closed – Local Traffic Only. (See Attached Closure For Reference)
Equipment Tie-Ins & Conduit Installation – Sunset Ave Between Bradley Pl. and N. County Rd. – Lane Closure – Local Traffic Only – Traffic Maintained
COCOANUT ROW WATERMAIN
Installation of New Watermain – Southbound Lane Closure – Cocoanut Row Between Royal Poinciana Way and Pendleton. Lane Closure To Be Implemented – Flagging Operation To Be Implemented -Traffic Maintained **All Phases Subject To Change*