Traffic impacts below for the week of 08/10/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List items – Various Locations – No Traffic Impact
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Overhead Wreck Out – Pole & Wire Removal – North County Road – Breaker Row to Royal Poinciana – Lane Closure – Traffic Maintained
Overhead Wreck Out – Pole & Wire Removal – Royal Poinciana Between North County Road & Cocoanut Row – Lane Closure – Traffic Maintained
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
Install Service Conduits (Back Yards) – Various Locations – No Traffic Impacts
Primary & Secondary Wire Pulling – Various Locations – Traffic Maintained
PHASE 8
Horizontal Directional Drilling / Undergrounding
HDD services on Root Trail between N. County and N. Ocean – Road Closed – Local Traffic Only. (See Attached Closure For Reference)
HDD (Easements) On Sunset Ave Between Bradley Place and N. County Road. – Traffic Maintained
HDD (Mainline & Services) On Sunrise Between N. County and S. Ocean – Lane Closure – Local Traffic Only – Traffic Maintained
Equipment Tie-Ins & Conduit Installation – Sunset Ave Between Bradley Pl. and N. County Rd. – Lane Closure – Local Traffic Only – Traffic Maintained
Concrete Restoration – 150 Bradley & 143 Seminole – No Trafic Impacts
COCOANUT ROW WATERMAIN
Installation of New Watermain – Southbound Lane Closure – Cocoanut Row Between Royal Poinciana Way and Pendleton. Lane Closure To Be Implemented – Flagging Operation To Be Implemented -Traffic Maintained