Lane Closure

Traffic impacts below for the week of 11/23/2026 for Phases 6S, 7N, 7S, 8, and the Cocoanut Row Watermain Projects.

**WORK ON WEDNESDAY 11/25/2026 IS RESTRICTED TO A 1/2 DAY FOR CLEAN UP & SITE RESTORATION**

**THERE IS NO WORK PERMITTED THURSDAY 11/26/2026, AND FRIDAY 11/27/2026 IN OBSERVANCE OF THE THANKSGIVING HOLIDAY**

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

Overhead Wreck Out – (Monday Through Wednesday) – Pole & Wire Removal On North Ocean – ROAD CLOSED LOCAL TRAFFIC ONLY

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

No Work Planned

PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

Testing of FPL Feeder Cable – Various Locations – No Traffic Impacts

Connections To Transformers & Switches  – Various Locations – No traffic impacts

General Clean-Up In Various Locations Throughout The Project – No Traffic Impacts

PHASE 8

Horizontal Directional Drilling / Undergrounding

HDD mainline conduits on N. County Rd from Sunrise to Royal Poinciana– Lane Closures will be implemented – Traffic Maintained

Tie-in on N. County Rd. from Everglade to Sunset – Lane Closures will be implemented – Traffic Maintained

Tie-in conduits on Seminole between Bradley Pl and N. County Rd. – Lane Closures will be implemented – Traffic Maintained

COCOANUT ROW WATERMAIN

Miscellaneous Punch List Items – No Traffic Impacts

**All Projects Subject To Change**