Traffic Impacts for the Week of 10/02/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 4 NORTH Horizontal Directional Drilling / Undergrounding Awaiting FPL Pole Removal PHASE 5 NORTH Horizontal Directional Drilling / Undergrounding HDD – Via Linda from N. Lake WAY (West) To The Cul De Sac – “Road Closed” Local Traffic Only-Traffic Maintained. Wire Pulling – Primary & Secondary – Various Locations – Lane Closure – […]