Entries by Town of Palm Beach

­Traffic Impacts for the Week of 04/29/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 4 NORTH FPL – Pole Removal Via Crane on List Road & Orange Grove Road – “Road Closed Local Traffic Only” PHASE 5 NORTH Horizontal Directional Drilling / Undergrounding Private Side Service Conversions – Various Locations – Pending Release of FPL Switching OrdersRestoration & Clean Up – Various Locations – No Traffic Impacts PHASE […]

­Traffic Impacts for the Week of 04/22/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 4 NORTH FPL – Pole Removal Via Crane on List Road – “Road Closed Local Traffic Only” PHASE 5 NORTH Horizontal Directional Drilling / Undergrounding Private Side Service Conversions – Various Locations – Pending Release of FPL Switching Orders PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Terminations – Various Locations – No Traffic […]

­Traffic Impacts for the Week of 04/15/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 4 NORTH FPL – Pole Removal Via Crane on Monterey & List Road – “Road Closed Local Traffic Only” PHASE 5 NORTH Horizontal Directional Drilling / Undergrounding Private Side Service Conversions – Various Locations – Pending Release Of FPL Switching Orders PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Terminations – Various Locations – […]

­Traffic Impacts for the Week of 04/08/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 4 NORTH FPL – Pole Removal (8 Each)  Via Crane on Monterey – “Road Closed Local Traffic Only” PHASE 5 NORTH Horizontal Directional Drilling / Undergrounding HDD (COMCAST) – Northlake Way Between Via Linda & Polmer Park Road – Lane Closure To Be Implemented – Traffic Maintained North Ocean – PBCC Parking Area – […]

­Traffic Impacts for the Week of 04/01/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 4 NORTH FPL – Pole Removal Via Crane on Colonial (First Part of Week) – “Road Closed Local Traffic Only” FPL – Pole Removal Via Crane on Queens Lane (Latter Part of Week) – “Road Closed Local Traffic Only” PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding HDD (COMCAST) – Northlake Way Between Cherry […]

­Traffic Impacts for the Week of 03/25/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 4 NORTH FPL – Pole Removal Via Crane on El Pueblo Way (Monday & Tuesday) – “Road Closed Local Traffic Only” FPL – Pole Removal Via Crane on Queens Lane (Wednesday, Thursday, & Friday) – “Road Closed Local Traffic Only” PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding HDD (COMCAST) – Northlake Way Between Cherry Lane […]

­Traffic Impacts for the Week of 03/18/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 4 NORTH FPL – Pole Removal Via Crane on El Pueblo Way (Monday, Tuesday, and maybe some on Wednesday) – “Road Closed Local Traffic Only” FPL – Pole Removal Via Crane on Queens Lane (Wednesday, Thursday, Friday) – “Road Closed Local Traffic Only” PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding Private Side Conversions […]

­Traffic Impacts for the Week of 03/11/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 4 NORTH FPL Will Continue Wire and Pole Removal Along North Ocean Blvd. Intermittent lane closures expected as necessary. PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding Private Side Conversions – No Traffic Impacts PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Wire Pulling & Terminations – Various Locations – No Traffic Impacts – Traffic […]

Traffic Impacts for the Week of 03/04/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 4 NORTH FPL Will Continue Wire And Pole Removal Along North Ocean Blvd. between Queens Ln and Monterey Rd. Intermittent lane closures expected as necessary. PHASE 5 NORTH   Horizontal Directional Drilling / Undergrounding Private Side Conversions –  – No Traffic Impacts PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Wire Pulling & Terminations – […]