Traffic Impacts for the week of 10/20/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8, and Clarke Alley

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Punch List – Replace FPL Feeder Box Lid When Supplied By FPL – No Impacts  PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Residential Conversions as FPL Releases Final Orders – Various Locations  PHASE 4 SOUTH Horizontal Directional Drilling / Undergrounding Overhead Wreckout and Pole Removal Along […]

Traffic Impacts for the week of 10/13/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8, and Clarke Alley

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Punch List Complete – Schedule Walk Through – No Impacts  PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Residential Conversions As FPL Releases Final Orders – Various Locations  PHASE 4 SOUTH Horizontal Directional Drilling / Undergrounding Overhead Wreckout and Pole Removal Along Brazilian Ave. Working West to […]

Traffic Impacts for the week of 10/06/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8, and Clarke Alley

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Finalize Punch List – Various Locations PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Residential Conversions as FPL Releases Final Orders – Various Locations  PHASE 4 SOUTH Horizontal Directional Drilling / Undergrounding Overhead Wreckout and Pole Removal. The Area will encompass Brazilian Ave., Chilean Ave., and Hibiscus […]

Traffic impacts for the week of 09/29/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8, and Clarke Alley

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Finalize Punch List – Various Locations PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Residential Conversions – Various Locations PHASE 4 SOUTH Horizontal Directional Drilling / Undergrounding Overhead pole removal on Brazilian working east from Hibiscus. PHASE 5 SOUTH Horizontal Directional Drilling / Undergrounding Overhead pole removal […]

Traffic impacts for the week of 09/22/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8, and Clarke Alley

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Finalize Punch List – Various Locations PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Residential Conversions – Various Locations PHASE 4 SOUTH Horizontal Directional Drilling / Undergrounding Overhead Wreckout and Pole Removal. The Area Will Encompass Australian Ave To Peruvian. Cocoanut Row To County Road. PHASE 5 […]

Traffic impacts for the week of 09/15/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8, and Clarke Alley

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Finalize Punch List – Various Locations PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Residential Conversions – Various Locations PHASE 4 SOUTH Horizontal Directional Drilling / Undergrounding Begin Overhead Wreckout and Pole Removal. The Area Will Encompass Brazilian To Chilean. S. Lake Drive To County Road. PHASE 5 […]

Traffic Impacts for the week of 09/08/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8, and Clarke Alley

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Finalize Punch List – Various Locations PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Residential Conversions – Various Locations PHASE 4 SOUTH Horizontal Directional Drilling / Undergrounding Begin Overhead Wreckout and Pole Removal. The Area Will Encompass Brazilian To Chilean. S. Lake Drive To South Ocean Blvd. PHASE […]

Traffic impacts for the week of 09/01/2025 for Phases 6N, 7N, 3S,4S, 5S, 6S, 7S, Phase 8, and Clarke Alley

~Monday September 1st is Labor Day, there is no work permitted on this day~ PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Finalize Punch List – Various Locations – No Traffic Impacts PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Residential Conversions – Various Locations – No Traffic Impacts PHASE 3 SOUTH No work scheduled. […]

Traffic impacts for the week of 08/25/2025 for Phases 6N, 7N, 3S,4S, 5S, 6S, 7S, Phase 8, and Clarke Alley

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Finalize Punch List – Various Locations – No Traffic Impacts PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Residential Conversions – Various Locations – No Traffic Impacts PHASE 3 SOUTH Concrete Curb – Golfview Rd. at corner south of Everglades Club (Pour early part of next week, […]

Traffic impacts for the week of 08/18/2025 for Phases  6N, 7N, 3S,4S, 5S, 6S, 7S, Phase 8, and Clarke Alley.

PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Finalize Punch List – Various Locations – No Traffic Impacts PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding Residential Conversions – Various Locations – No Traffic Impacts PHASE 3 SOUTH Concrete Curb – Golfview Road At Corner South Of Everglades Club – Pending Concrete Scheduling Concrete Curb […]