Traffic Impacts for the Week of 09/04/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects
**NO WORK PERMITTED MONDAY SEPTEMBER 4TH IN OBSERVANCE OF THE LABOR DAY HOLIDAY** PHASE 4 NORTH Horizontal Directional Drilling / Undergrounding Awaiting FPL Pole Removal Schedule Punch List Items – Various Locations – Traffic Maintained PHASE 5 NORTH Horizontal Directional Drilling / Undergrounding Pulling Feeder – (The Cut) From The Intersection of Country Club Road […]