Traffic Impacts for the Week of 1/27/2025 for the Phase 5 North, Phase 6 North, Phase 7 North*, Phase 3 South, Phase 4 South, Phase 5 South, Phase 6 South, and Phase 7 South Projects (*Updated on 1/29/2025)
PHASE 5 NORTH Horizontal Directional Drilling / Undergrounding No work scheduled PHASE 6 NORTH Horizontal Directional Drilling / Undergrounding Complete Switching Orders – Various Locations As Released By FPL PHASE 7 NORTH Horizontal Directional Drilling / Undergrounding HDD – N. Ocean Blvd. – ROAD CLOSED, Jamaica Ln to Sandpiper Dr. – Detour To Be Implemented. […]