Lane Closure

Traffic Impacts for the Week 11/20/2023 for the Phase 5 North, Phase 6 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects

**THERE WILL BE NO WORK PERMITTED ON THURSDAY 11/23/2023 THANKSGIVING & FRIDAY 11/24/2023**

PHASE 5 NORTH 

Horizontal Directional Drilling / Undergrounding

Equipment & Conduit installation – N. Lake Way between Ridgeview & Via Linda – Lane closure to be implemented – Traffic Maintained.

Equipment & Conduit installation – West Side of Via Linda between the cul-de-sac & N. Lake Way – “Road Closed” Local Traffic Only – Traffic Maintained

Conduit & Equipment Installation –  W. Indies between N. Lake Way & N. County Road – “Road Closed” Local Traffic Only – Traffic Maintained.

Pulling Wire & Terminations – Various Locations – No Traffic Impacts

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – Miraflores Between Northlake Way & North County Road – Road Closed – Local Traffic Only – Traffic Maintained

HDD (Services) –  Casa Bendita between N. County Road (East) to the cul-de-sac – “Road Closed” Local Traffic Only – Traffic Maintained

Equipment & Conduit Installation – Miraflores Between Northlake Way & N. County Road – Road Closed – Local TrafficOnly – Traffic Maintained

Equipment & Conduit Installation – Casa Bendita Between N. County Road and the cul-de-sac.  Road Closed – Local Traffic Only – Traffic Maintained

Wire Pulling & Terminations – Various Locations – No Traffic Impacts

PHASE 2 SOUTH

Horizontal Directional Drilling / Undergrounding

Punch List Items

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Continue conversions, switching orders, and misc. punch list items.

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Conduit connections, equipment installation, and road restorations on Brazilian Avenue between Hibiscus Avenue and South Ocean Boulevard.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Awaiting switching orders. Miscellaneous Terminations.

Sidewalk repairs on Brazilian Avenue & Australian Avenue.

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

No Work Scheduled

“LOCAL TRAFFIC ONLY” 

**All Phases Subject To Change**