Traffic Impacts for the Week of 01/09/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 2 South, Phase 3 South, Phase 4 South, and Phase 5 South Projects
PHASE 4 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Service Connections — Various Locations – Traffic Maintained
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – Plantation Road, Southland Road Between Northlake Way & N. County Road –
HDD – Northlake Way Between El Dorado & Plantation Road – Lane Closure to be Implemented – Traffic Maintained.
Pulling Primary Wire on Cherry Lane & Windsor Court – Traffic Maintained.
Equipment & Conduit Installation – Via Linda, Southland Road Between Northlake Way & North County Road – Road Closed Local Traffic Only – Traffic Maintained
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – Main Line Feeder Conduits – Kawama Lane – N. County Road To Northlake Way – Road Closed
Local Traffic Only – Traffic Maintained
PHASE 2 SOUTH
Horizontal Directional Drilling / Undergrounding
Miscellaneous Feeder Energized In The Projects Limits Depending on FPL Orders Being Released.
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Miscellaneous cable installation and equipment makeup throughout the phase.
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD on Australian Avenue between Hibiscus Avenue and South Ocean Boulevard.
HDD on South Ocean Boulevard between Peruvian Avenue and Brazilian Avenue.
HDD on South County Road from Worth Avenue north to Brazilian Avenue. (Lane shift)
HDD services 300 block of Chilean Avenue.
Conduit connections, equipment installation, and road restorations on Peruvian Avenue between
Hibiscus Avenue and South Ocean Blvd. and on Chilean Avenue between Hibiscus Avenue and South Ocean Blvd.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD on Brazilian Avenue between Hibiscus Avenue and South Lake Drive.
HDD on Seaspray Avenue between Cocoanut Row and South Ocean Boulevard.
HDD on Cocoanut Row between Seaview Avenue and Seabreeze Avenue.
Conduit connections, equipment installation, and road restorations on Peruvian Avenue between South Lake Drive and Cocoanut Row.
“LOCAL TRAFFIC ONLY”