Lane Closure

Traffic Impacts for the Week of 03/13/2023 for the Phase 4 North, Phase 5 North,  Phase 6 North, Phase 3 South, Phase 4 South, and Phase 5 South Projects

PHASE 4 NORTH 

Horizontal Directional Drilling / Undergrounding

Private Side Service Connections — Various Locations (Dependent on FPL Switching Orders) – Traffic Maintained

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

Equipment & Conduit Installation – Northlake Way Between Cherry Lane & Plantation – Lane Closure To Be Implemented  – Traffic Maintained

Equipment & Conduit Installation – Plantation Road Between Northlake Way & Crest Road –  Road Closed Local Traffic Only – Traffic Maintained

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – North County Road – Main Line (Bike Path) Between Kawama Lane & Bermuda – Pedestrian Traffic Maintained

HDD –  North Woods Road – Main Line – Between E. Woods And The Intracoastal

HDD – South Woods Road – Main Line – Between N. County Road And The Intracoastal

Equipment & Conduit Installation – Kawama Lane & North County Road (Bike Path) – Pedestrian Traffic Maintained

PHASE 2 SOUTH

No Further Reports Until Pole Removal Begins

PHASE 3 SOUTH 

Miscellaneous equipment verification and switching orders.

Horizontal Directional Drilling / Undergrounding 

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on South Ocean Boulevard between Peruvian Avenue and Brazilian Avenue.

HDD on Brazilian Avenue between Hibiscus Avenue and South Ocean Boulevard.

HDD on South County Road between Royal Palm Way and Australian Avenue.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Brazilian Avenue between Hibiscus Avenue and South Lake Drive.

HDD on Cocoanut Row between Royal Palm Way and Peruvian Avenue.

HDD on Seaspray Avenue between South County Road and South Ocean Boulevard.

HDD on South County Road between Royal Palm Way and Seabreeze Avenue.

HDD on Seaview Avenue between South County Road and South Ocean Boulevard.

HDD services in the 400 and 300 blocks of Brazilian Avenue and Australian Avenue.

Conduit connections, equipment installation, & road restorations on Chilean Avenue between South Lake Drive and Cocoanut Row, on Cocoanut Row between Worth Avenue and Chilean Avenue, and on Seaspray Avenue west of Cocoanut Row.

“LOCAL TRAFFIC ONLY”.  If you have any questions or concerns please let me know.

**All Phases Subject to Change**