Notice of Construction – P1 North – Overhead to Underground Power Conversions

Notice of Construction – P1 North – Overhead to Underground Power Conversions

The Town and its contractors obtained overhead to underground electrical switching orders from FPL and established a schedule estimating the dates of work throughout the Phase 1 North Area.  Beginning on 1/2/19 through 1/4/19 work will be performed on the primary lines and transformers throughout the entire area. 

During the first week of January, Burkhardt Construction will inform impacted residents in the initial area (Area #1 shown on the map) of pending cutovers during Jan 7th-18th.  As we get closer to the time to convert Areas #2 & #3, Burkhardt will inform those residents. 

The schedule may be adjusted as required.

If you have any questions, feel free to call or email undergrounding info at 561-227-7077 or Underground@TownofPalmBeach.com.