Traffic impacts below for the week of 03/23/2026 for Phases 6N, 7N, 4S, 5S, 6S, 7S, and Phase 8.
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List – Verify Completion Of Punch List – No Traffic Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Miscellaneous Punch List Items No Traffic Impacts
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Miscellaneous Punch List Items – No Traffic Impacts
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Prep and Complete Any Remaining Conversions – No Traffic Impacts.
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling – East End Of Sanford Between N. County & North Lakeway – “ROAD CLOSED” – Local Traffic Only – Traffic Maintained
HDD Drilling – (Mainline) – East End Of Dunbar Between N. County Road & North Ocean Blvd. – “ROAD CLOSED” – Local Traffic Only – Traffic Maintained
Equipment & Conduit installation – Dunbar Road (East) between N. County Rd & N. Ocean Blvd – “ROAD CLOSED” – Local Traffic Only – Traffic Maintained
Equipment & Conduit Installation – Atlantic Ave Between Bradley Place & N. County Road – “ROAD CLOSED” – Local Traffic Only – Traffic Maintained
Wire Pulling – Various Locations – No Traffic Impacts.
PHASE 8
Horizontal Directional Drilling / Undergrounding
HDD On Seminole Between N. County and North Ocean – Lane Closure To Be Implemented – Traffic Maintained
HDD On Root Trail Between N. County and North Ocean – Lane Closure To Be Implemented – Traffic Maintained
**All Phases Subject To Change**