Traffic Impacts for the Week 07/17/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects
PHASE 4 NORTH
Horizontal Directional Drilling / Undergrounding
Awaiting FPL Pole Removal Schedule
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Pulling Wire – Plantation & Crest Road – “Road Closed Local Traffic Only” Traffic Maintained.
Equipment & Conduit Installation – Northlake Way Between Ridgeview & El Dorado- Lane Closure To Be Implemented – Traffic Maintained
Equipment & Conduit Installation – Windsor Ct. Between N. County Road & Cherry Lane – “Road Closed Local Traffic Only” Traffic Maintained.
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – Tangier Ave. Between Northlake Way & N. County Road – “Road Closed Local Traffic Only” – Traffic Maintained
Equipment & Conduit Installation – N. Lake Way Between Tangier & Sanford – Lane Closure To Be Implemented – Traffic Maintained
Equipment & Conduit Installation – Miraflores Dr. Between Northlake Way & N. County Road – “Road Closed Local Traffic Only” – Traffic Maintained
Equipment & Conduit Installation – Tangier From Northlake Way Heading West Towards Lake Trail- “Road Closed Local Traffic Only” – Traffic Maintained
PHASE 2 SOUTH
Horizontal Directional Drilling / Undergrounding
Pole removal south of Southern Blvd.. Road closures during removal.
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Miscellaneous equipment verification and switching orders – (FPL Feeder Orders)
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD on Australian Avenue between South Ocean Boulevard and Hibiscus Avenue.
HDD on Brazilian Avenue between South Ocean Boulevard and Hibiscus Avenue.
HDD on Hibiscus Avenue between Chilean Avenue and Royal Palm Way.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Conduit connections, equipment installation, and road restorations on South County Road between Seabreeze Avenue and Royal Palm Way, on Cocoanut Row between Royal Palm Way and Seaspray Avenue, and on Seaview Road between South Ocean Boulevard and Cocoanut Row.
Miscellaneous cable pulling in the 300 & 400 blocks of the project limits.
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Clarke/Barton Alleyways between Cocoanut Row and South Ocean Boulevard.
“LOCAL TRAFFIC ONLY”
**All Phases Subject to Change**