Lane Closure

Traffic Impacts for the Week 07/17/2023 for the Phase 4 North, Phase 5 North,  Phase 6 North, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects

PHASE 4 NORTH 

Horizontal Directional Drilling / Undergrounding

Awaiting FPL Pole Removal Schedule

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

Pulling Wire – Plantation & Crest Road –  “Road Closed Local Traffic Only” Traffic Maintained.

Equipment & Conduit Installation – Northlake Way Between Ridgeview & El Dorado- Lane Closure To Be Implemented – Traffic Maintained 

Equipment & Conduit Installation – Windsor Ct. Between N. County Road & Cherry Lane  – “Road Closed Local Traffic Only” Traffic Maintained.

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – Tangier Ave. Between Northlake Way & N. County Road  –  “Road Closed Local Traffic Only” – Traffic Maintained

Equipment & Conduit Installation – N. Lake Way Between Tangier & Sanford –  Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – Miraflores Dr. Between Northlake Way & N. County Road –  “Road Closed Local Traffic Only” – Traffic Maintained

Equipment & Conduit Installation – Tangier From Northlake Way Heading West Towards Lake Trail-  “Road Closed Local Traffic Only” – Traffic Maintained

PHASE 2 SOUTH

Horizontal Directional Drilling / Undergrounding

Pole removal south of Southern Blvd.. Road closures during removal.

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Miscellaneous equipment verification and switching orders – (FPL Feeder Orders)

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Australian Avenue between South Ocean Boulevard and Hibiscus Avenue.

HDD on Brazilian Avenue between South Ocean Boulevard and Hibiscus Avenue.

HDD on Hibiscus Avenue between Chilean Avenue and Royal Palm Way.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Conduit connections, equipment installation, and road restorations on South County Road between Seabreeze Avenue and Royal Palm Way, on Cocoanut Row between Royal Palm Way and Seaspray Avenue, and on Seaview Road between South Ocean Boulevard and Cocoanut Row.

Miscellaneous cable pulling in the 300 & 400 blocks of the project limits.

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD Clarke/Barton Alleyways between Cocoanut Row and South Ocean Boulevard.

“LOCAL TRAFFIC ONLY”

**All Phases Subject to Change**