Traffic Impacts for the Week of 11/27/2023, for the Phase 5 North, Phase 6 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Equipment & Conduit installation – N. Lake Way between Palmo Park & Via Linda – Lane Closure to be Implemented – Traffic Maintained.
Pulling Wire & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – Northlake Way Between the D-4 Pump Station & South Woods Road – Lane Closure To Be Implemented – Traffic Maintained
HDD (Services) – Casa Bendita between N. County Road (East) to the cul-de-sac – “Road Closed” Local Traffic Only – Traffic Maintained
Equipment & Conduit Installation – Tangier, Miraflores Between Northlake Way & N. County Road – Road Closed – Local TrafficOnly – Traffic Maintained
Equipment & Conduit Installation – Casa Bendita Between N. County Road and the cul-de-sac. Road Closed – Local TrafficOnly – Traffic Maintained
Wire Pulling & Terminations – Various Locations – No Traffic Impacts
PHASE 2 SOUTH
Horizontal Directional Drilling / Undergrounding
Punch List Items
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue conversions and punch list items.
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Conduit connections, equipment installation, and road restorations on Brazilian Avenue between South County and South Ocean Boulevard.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Awaiting switching orders. Miscellaneous Terminations.
Sidewalk repairs on Brazilian Avenue & Australian Avenue.
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD on Seabreeze Avenue west of Cocoanut Row, Barton Avenue Alley, and Cocoanut Row between Seaspray Avenue and Barton Avenue.
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**