Lane Closure

Traffic Impacts for the Week 12/04/2023 for the Phase 5 North, Phase 6 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

Pulling Wire & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – Northlake Way Between North Woods Road & Kawama – Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – Tangier, Miraflores Between Northlake Way & N. County Road – Road Closed – Local Traffic Only – Traffic Maintained

Equipment & Conduit Installation – Casa Bendita Between N. County Road and the cul-de-sac.  Road Closed – Local Traffic Only – Traffic Maintained

Equipment Terminations – Various Locations – No Traffic Impacts

PHASE 2 SOUTH

Horizontal Directional Drilling / Undergrounding

Punch List Items

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Continue conversions, punch list items, remaining switching orders.

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Conduit connections, equipment installation, and road restorations on Brazilian Avenue between South County and South Ocean Boulevard.

Sidewalk repairs on Brazilian Avenue and Australian Avenue.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Awaiting switching orders. Miscellaneous Terminations.

Sidewalk repairs on Brazilian Avenue & Australian Avenue.

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Seabreeze Avenue west of Cocoanut Row, Via Sunny, and Cocoanut Row between Seaspray Avenue and Barton Avenue.

“LOCAL TRAFFIC ONLY” 

**All Phases Subject To Change**