Lane Closure

Traffic impacts for the week of 01/12/2026 for Phases  6N, 7N,4S, 5S, 6S, 7S, and Phase 8.

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Punch List – Replace FPL Feeder Box Lid – Awaiting FPL Delivery – No Traffic Impacts

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

HDD Drilling – (AT&T) – North Ocean Between Bahama Lane & North End Of Palm Beach Country Club Parking Lot – Lane Closure To Be Implemented – Traffic Maintained

HDD Drilling – (AT&T) – Northlake Way From Via Marila & Bahama Lane – Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – Alley Between Garden & Eden – “ROAD CLOSED” – Local  Traffic Only – Traffic Maintained

Pulling Feeder – Northlake Way Between List Road & Eden – Lane Closure To Be Implemented – Traffic Maintained

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding 

Complete Miscellaneous Punch List Items  No Traffic Impacts

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Work on miscellaneous punch list items – No Traffic Impacts

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Prep and Execute SO’s As They Become Available – Various Locations

Prep and Complete Any Remaining Conversions – No Traffic Impacts

Complete Installation Of Traffic Controller Breakers & Street Lighting Controls – No Traffic Impacts

PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD Drilling – Atlantic Road Between N. County Road & Bradley Place – “ROAD CLOSED” – Local  Traffic Only – Traffic Maintained

HDD Drilling – Northlake Way Between Wells Road & Sanford – Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – Atlantic Ave Between Bradley Place & N. County Road –  “ROAD CLOSED” – Local  Traffic Only – Traffic Maintained

PHASE 8

Horizontal Directional Drilling / Undergrounding

No Work Scheduled – No Traffic Impacts

**All Phases Subject To Change*