Traffic Impacts for the Week of 01/15/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Pulling Wire & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Equipment & Conduit Installation – Casa Bendita Between North County Road and the Cul-de-sac – Road Closed Local Traffic Only – Traffic Maintained
Equipment & Conduit Installation – Northlake Way Between Tangier & Miraflores – Road Closed Local Traffic Only – Traffic Maintained
Wire Pulling & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – N. Lake Trail – From The Rock Cut North To Bahama Lane – Lane Closure – Traffic Maintained
PHASE 2 SOUTH
Horizontal Directional Drilling / Undergrounding
Punch List Items
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue conversions and remaining switching orders.
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Conduit connections, equipment installation, and road restorations on Australian Avenue between South County Road and South Ocean Blvd. and South Ocean Boulevard between Chilean Avenue and Brazilian Avenue.
Miscellaneous cable installation in southern portions of the phase.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Switching orders. Begin conversions as allowable.
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD on Seabreeze Avenue west of Cocoanut Row, Antigua Lane, Primavera Avenue, and Cocoanut Row between Seaspray Avenue and Barton Avenue.
HDD on Barton Avenue between Cocoanut Row and South County Road.
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**