Traffic impacts for the week of 02/09/2026 for Phases 6N, 7N,4S, 5S, 6S, 7S, and Phase 8.
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List – Replace FPL Feeder Box Lid – Not Scheduled This Week
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Equipment & Conduit Installation – Alley Between Garden & Eden – “ROAD CLOSED” – Local Traffic Only – Traffic Maintained
Equipment & Conduit installation – NoN. Lake Way between VIA MARILA & Bahama Lane – Lane Closure to be implemented – Traffic Maintained
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Miscellaneous Punch List Items No Traffic Impacts
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Work on miscellaneous punch list items – No Traffic Impacts
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Prep and execute SO’s as they become available.
Prep and complete any remaining conversions, no traffic impacts.
Complete installation of street lighting controls, no traffic impacts.
Install Breakers CT cabinet – Temporary Lane Closure to be implemented East side Northbound Lane. Sidewalk to also closed to pedestrians. Will coordinate the date once confirmed.
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling (ATT Fiber) – Crescent Drive between N. County Rd. & Wells Road – “ROAD CLOSED” – Local Traffic Only – Traffic Maintained
HDD Drilling – Atlantic Ave. Between Bradley Place & N. County Road – “ROAD CLOSED” – Local Traffic Only – Traffic Maintained
Equipment & Conduit installation – N. Lake Way between Kawama & Wells Road – Lane Closure to be implemented – Traffic Maintained
PHASE 8
Horizontal Directional Drilling / Undergrounding
No Work Scheduled – No Traffic Impacts
**All Phases Subject To Change**