Lane Closure

­Traffic Impacts for the Week of 03/18/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 4 NORTH

FPL – Pole Removal Via Crane on El Pueblo Way (Monday, Tuesday, and maybe some on Wednesday) – “Road Closed Local Traffic Only”

FPL – Pole Removal Via Crane on Queens Lane (Wednesday, Thursday, Friday) – “Road Closed Local Traffic Only”

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

Private Side Conversions –  – No Traffic Impacts

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Wire Pulling & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

HDD (Services) – Bahama Lane Between Northlake Way & North Ocean Blvd. – “Road Closed Local Traffic Only” – Traffic Maintained

HDD – (Services) Northlake Way From Tradewinds To Eden – “ROAD CLOSED” Approved Detour To Be Implemented – Monday 3/18/24 Through Wednesday 3/20/2024

HDD – Alley Between Sandpiper & Eden From Northlake Way To North Ocean –  “Road Closed” Local Traffic Only Where Accessible

HDD – Jamaica Lane Between Northlake Way & North Ocean – “Road Closed Local Traffic Only” – Traffic Maintained

Equipment & Conduit Installation – Northlake Way Between Tradewinds & Eden –  “ROAD CLOSED” – Approved Detour To Be Implemented – Monday 3/18/24 Through Wednesday 3/20/2024

Equipment & Conduit Installation – Bahama Lane Between Northlake Way & North Ocean Blvd. –  “Road Closed Local Traffic Only” – Traffic Maintained

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Continue conversions and remaining switching orders as they are released by FPL.

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Cable Installation Throughout The Phase 

Device Installation and Terminations Throughout The Phase

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Switching orders as they are released by FPL. Continue conversions as allowable.

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Cocoanut Row between Clarke Avenue and Whitehall Way.

HDD on Pendleton Avenue between intracoastal and South County Road.

HDD on Chapel Hill Road.
Conduit connections, equipment installation, and road restorations on Seabreeze Avenue between South County Road and the intracoastal.

“LOCAL TRAFFIC ONLY”  **All Phases Subject to Change**