PHASE 4 NORTH
FPL – Pole Removal Via Crane on El Pueblo Way (Monday, Tuesday, and maybe some on Wednesday) – “Road Closed Local Traffic Only”
FPL – Pole Removal Via Crane on Queens Lane (Wednesday, Thursday, Friday) – “Road Closed Local Traffic Only”
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Conversions – – No Traffic Impacts
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Wire Pulling & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
HDD (Services) – Bahama Lane Between Northlake Way & North Ocean Blvd. – “Road Closed Local Traffic Only” – Traffic Maintained
HDD – (Services) Northlake Way From Tradewinds To Eden – “ROAD CLOSED” Approved Detour To Be Implemented – Monday 3/18/24 Through Wednesday 3/20/2024
HDD – Alley Between Sandpiper & Eden From Northlake Way To North Ocean – “Road Closed” Local Traffic Only Where Accessible
HDD – Jamaica Lane Between Northlake Way & North Ocean – “Road Closed Local Traffic Only” – Traffic Maintained
Equipment & Conduit Installation – Northlake Way Between Tradewinds & Eden – “ROAD CLOSED” – Approved Detour To Be Implemented – Monday 3/18/24 Through Wednesday 3/20/2024
Equipment & Conduit Installation – Bahama Lane Between Northlake Way & North Ocean Blvd. – “Road Closed Local Traffic Only” – Traffic Maintained
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue conversions and remaining switching orders as they are released by FPL.
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Cable Installation Throughout The Phase
Device Installation and Terminations Throughout The Phase
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Switching orders as they are released by FPL. Continue conversions as allowable.
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD on Cocoanut Row between Clarke Avenue and Whitehall Way.
HDD on Pendleton Avenue between intracoastal and South County Road.
HDD on Chapel Hill Road.
Conduit connections, equipment installation, and road restorations on Seabreeze Avenue between South County Road and the intracoastal.
“LOCAL TRAFFIC ONLY” **All Phases Subject to Change**