Traffic Impacts for the Week of 04/08/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 4 NORTH
FPL – Pole Removal (8 Each) Via Crane on Monterey – “Road Closed Local Traffic Only”
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
HDD (COMCAST) – Northlake Way Between Via Linda & Polmer Park Road – Lane Closure To Be Implemented – Traffic Maintained
North Ocean – PBCC Parking Area – Section of South End Of Parking Area Along the West Side Of North Ocean To Be Blocked Off To Complete Switch Terminations – Pending FPL Switching Orders
Private Side Service Conversions – Various Locations – Awaiting FPL Switching Orders
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Terminations – Various Locations – No Traffic Impacts – Traffic Maintained
Curb Removal & Replacement – Various Locations – No Traffic Impacts – Traffic Maintained
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – Alley Between Sandpiper & Eden From Northlake Way To North Ocean – “Road Closed” – No Through Traffic
HDD – Jamaica Lane Between Northlake Way & North Ocean – “Road Closed Local Traffic Only” – Traffic Maintained
Equipment & Conduit Installation – Jamaica Lane Between Northlake Way & North Ocean Blvd. – “Road Closed Local Traffic Only” – Traffic Maintained
Equipment & Conduit Installation – Alley Between Sandpiper & Eden From Northlake Way To North Ocean – “Road Closed” – No Through Traffic
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue conversions and remaining switching orders as they are released by FPL.
HDD – Island Drive – (FPL Work)
Conduit connections, equipment installation, and road restorations on Island Drive.
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Cable Installation Throughout The Phase
Device Installation and Terminations Throughout The Phase
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Switching orders as they are released by FPL. Continue conversions as allowable.
Sidewalk restorations on Cocoanut Row and Seaview Avenue.
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Conduit connections, equipment installation, and road restorations on Seabreeze Avenue between South County Road and the intracoastal and in the Clarke Alleyway from South County Road to South Ocean Boulevard.
“LOCAL TRAFFIC ONLY”
**All Phases Subject to Change**