Traffic Impacts for the Week of 04/24/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, and Phase 5 South Projects
PHASE 4 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Service Connections — Various Locations (Dependent on FPL Switching Orders) – Traffic Maintained
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – (Services) N. Lake Way Between Cherry Ln & Via Linda – “Road Closed With Approved Detour”
Equipment & Conduit Installation – (Services) N. Lake Way Between Country Club Road & Via Linda – Work To Be Performed Concurrently Within Approved Detour.
Wire Pulling (Secondary) – Ridgeview & El Dorado Between Northlake Way & N. County Road – Traffic Maintained
Waterline Relocation & Hydrant – Plantation & Crest Road – Road Closed Local Traffic Only – Traffic Maintained
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – N. Lake Way Between Via Tortuga & S. Woods Road – Lane Closure To Be Implemented – Traffic Maintained
HDD – (Services) La Costa Way – Road Closed “LOCAL TRAFFIC ONLY” – Traffic Maintained
Equipment & Conduit Installation – N. Lake Way Between Via Tortuga & S. Woods Road – Lane Closure – Traffic Maintained
Equipment & Conduit Installation – Bermuda Lane – Road Closed “LOCAL TRAFFIC ONLY” – Traffic Maintained
PHASE 2 SOUTH
Horizontal Directional Drilling / Undergrounding
Switching orders on South Ocean Boulevard between Southern Boulevard and Via Del Lago. – FPL Dependent
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Miscellaneous equipment verification and switching orders – Various Locations – FPL Dependent
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Conduit connections, equipment installation, and road restorations on Cocoanut Row between Peruvian Avenue and Australian Avenue.
Various gas main relocations.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD on Cocoanut Row between Royal Palm Way and Australian Avenue.
HDD on South County Road between Royal Palm Way and Seabreeze Avenue.
HDD on South Ocean Boulevard between Royal Palm Way and Seabreeze Avenue
HDD on Royal Palm Way between Cocoanut Row and South County Road.
HDD on Seaview Ave between South County Rd and South Ocean Blvd.
HDD services on Seaview Avenue, Brazilian Avenue, Australian Avenue and Cocoanut Row.
Conduit connections, equipment installation, and road restorations on Cocoanut Row between Peruvian and Brazilian Avenue, on Australian Avenue between South Lake Drive and Hibiscus Avenue, on South Lake Drive between Australian Avenue and Royal Palm Way, and on Brazilian Avenue between South Lake Drive and Cocoanut Row.
Various gas main relocations.
PHASE 6 SOUTH
HDD at 321 Barton Pending Approved Plan Revision
“LOCAL TRAFFIC ONLY”
**All Phases Subject to Change**