Lane Closure

Traffic Impacts for the Week of 05/01/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, Phase 5 South, and Phase 6 South Projects

PHASE 4 NORTH 

Horizontal Directional Drilling / Undergrounding

Private Side Service Connections — Various Locations (Dependent on FPL Switching Orders) – Traffic Maintained

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

Wire Pulling (Secondary) – Windsor Court, Cherry Lane, & El Dorado Between Northlake Way & N. County Road – Traffic Maintained

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – N. Lake Way Between Miraflores & S. Woods Road – Lane Closure To Be Implemented – Traffic Maintained

HDD – N. Lake Way Between Plantation & S. Woods Road – Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – N. Lake Way Between Miraflores & N. Woods Road –  Lane Closure To Be Implemented – Traffic Maintained

Wire Pulling – Kawama Lane Between Northlake Way & North County Road – Road Closed “LOCAL TRAFFIC ONLY” – Traffic Maintained

Wire Pulling – Bermuda Lane Between North County Road & The Turn Around – Road Closed “LOCAL TRAFFIC ONLY” – Traffic Maintained

PHASE 2 SOUTH

Horizontal Directional Drilling / Undergrounding

Switching orders on South Ocean Boulevard between Southern Boulevard and Via Del Lago.

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Miscellaneous equipment verification and switching orders – Various Locations

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Conduit connections, equipment installation, and road restorations on Cocoanut Row between Peruvian Avenue and Australian Avenue.

Various gas main relocations.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Cocoanut Row between Royal Palm Way and Australian Avenue.

HDD on South County Road between Royal Palm Way and Seabreeze Avenue.

HDD on Royal Palm Way between Cocoanut Row and South County Road.

HDD services on Seaview Avenue, Brazilian Avenue, Australian and Hibiscus.

Conduit connections, equipment installation, and road restorations on Cocoanut Row between Chilean Avenue & Royal Palm Way, on Australian Avenue between Cocoanut Row and Hibiscus Avenue, and on Brazilian Avenue between Cocoanut Row and Hibiscus Avenue.

Various gas main relocations.

PHASE 6 SOUTH

HDD at 321 Barton Pending Approved Plan Revision

“LOCAL TRAFFIC ONLY”

**All Phases Subject to Change**